Skyline (Honolulu)
Skyline | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | Honolulu Department of Transportation Services | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | City and County of Honolulu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 9 (10 under construction, 2 planned) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Website | honolulu honolulutransit | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Rapid transit[1] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | Hitachi Rail | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock | Hitachi Rail Italy Driverless Metro | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Daily ridership | 3,000 (weekdays, Q2 2024) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Ridership | 614,800 (2023) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | June 30, 2023 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 10.8 mi (17.4 km) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of tracks | 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Character | Elevated | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 4 ft 8+1⁄2 in (1,435 mm) standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | Third rail, 750 V DC[2] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | 55[3] mph (89 km/h) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Skyline is a rapid transit system in the City and County of Honolulu on the island of Oʻahu, in the state of Hawaiʻi. Phase 1 of the project opened June 30, 2023 and lies entirely outside of the Urban Honolulu census-designated place, linking East Kapolei (on the ʻEwa Plain) and Aloha Stadium. Phase 2, connecting to Pearl Harbor and Daniel K. Inouye International Airport before reaching Middle Street, is anticipated to open in late 2025. The final phase, continuing the line across Urban Honolulu to Downtown, is due to open in 2031. Its construction constitutes the largest public works project in Hawaiʻi's history.
The 18.9-mile (30.4 km), automated fixed-guideway line was planned, designed, and constructed by the Honolulu Authority for Rapid Transportation (HART), a semi-autonomous government agency. Hitachi Rail, who also built the railcars used on the line, operates Skyline for the Honolulu Department of Transportation Services (which also manages the region's TheBus service). The almost entirely elevated line is the first large-scale, publicly run metro in the United States to feature platform screen doors and driverless trains. In 2023, the line had a monthly ridership of 614,800, or about 3,000 per weekday as of the second quarter of 2024.
History
[edit]Plans for a mass transit line to connect Honolulu's urban center with outlying areas began in the 1960s,[4] but funding was not approved until 2005.[5] Debate over the development of a rail system in Honolulu has been a major point of contention in local politics, especially leading into the 2008, 2012, and 2016 mayoral elections. Controversy over the rail line was the dominant issue for local politics in the late 2000s,[6] and culminated in a city charter amendment which left the final decision to a direct vote of the citizens of Oʻahu.[7] Construction of the rail line was approved by 53% of voters in November 2008,[8] and ground broke on project construction on February 22, 2011.[9][10]
Previous projects
[edit]For more than 50 years, some Honolulu politicians have attempted to construct a rail transit line. In 1966, then-mayor Neal S. Blaisdell suggested a rail line as a solution to alleviate traffic problems in Honolulu, stating, "Taken in the mass, the automobile is a noxious mechanism whose destiny in workaday urban use is to frustrate man and make dead certain that he approaches his daily occupation unhappy and inefficient."[4]
Frank Fasi was elected to office in 1968, and started planning studies for a rail project,[11] named Honolulu Area Rapid Transit (HART), in 1977.[12] After Fasi lost the 1980 reelection to Eileen Anderson, President Ronald Reagan cut off funding for all upcoming mass transit projects, which led Anderson to cancel HART in 1981.[13][14][15] Fasi defeated Anderson in their 1984 rematch and restarted the HART project in 1986,[16] but this second effort was stopped in a 1992 vote by the Honolulu City Council against the necessary tax increase.[5][17]
Fasi resigned in 1994 to run for governor, with Jeremy Harris winning the special election to replace him. Harris unsuccessfully pursued a bus rapid transit project as an interim solution until he left office in 2004.[18] His successor, Mufi Hannemann, began the Honolulu High-Capacity Transit Corridor Project (HHCTCP), the island's fourth attempt to build a mass transit system operating in a dedicated right-of-way.
Hannemann thought it was "prudent to move quickly" to show the FTA that Honolulu was committed to the HHCTCP. An environmental impact study had not been completed at the time of signing the first construction contract with Kiewit. The FTA needed a complete environmental impact statement before moving Honolulu forward in the grant-awarding process. Hannemann's urge to move fast in the project ultimately allowed stakeholders to delay some important foundational work such as the environmental impact study.[19]
Studies
[edit]The City and County of Honolulu Department of Transportation Services released the first formal study related to the HHCTCP on November 1, 2006, the Alternatives Analysis Report. The report compared the cost and benefits of a "fixed guideway system", along with three alternatives. The first expanded the existing bus system to match population growth. A second option called for a further expansion to the bus system, with improvements to existing roads. The third alternative proposed a two-lane flyover above the H-1 freeway between Pearl City and Honolulu International Airport, continuing over Nimitz Highway, and into downtown Honolulu. The report recommended construction of the fixed guideway, and is considered the city's official justification for building a rail line.[20][21]
A second planning document, the Draft Environmental Impact Statement (DEIS), studied possible natural and social impacts of the construction and operation of the HHCTCP. The DEIS was completed and cleared for public release by the Federal Transit Administration (FTA) on October 29, 2008. After minor changes were made to comply with state law, the document was distributed via the city's official project website four days later. The DEIS indicated that impacts of the rail project would include land acquisition from private owners on the route, displacement of residents and businesses, aesthetic concerns related to the elevated guideway, and noise from passing trains.[22]
The city was criticized for timing the release only two days before the 2008 general election. City Councilmember Ann Kobayashi, running as a mayoral candidate against incumbent Hannemann, suggested that the city deliberately withheld key information to early voters who had already cast their ballots for the mayoral candidates, and a city charter amendment related to the project.[23][24] The anti-rail advocacy group Stop Rail Now criticized the report for not further discussing bus rapid transit and toll lanes, options studied earlier by the city in its Alternatives Analysis.[25][26]
The third and final official planning document, the Final Environmental Impact Statement (FEIS), was approved and cleared for public release by the FTA on June 14, 2010. The FEIS addresses and incorporates public comments received regarding the DEIS.[27] The FTA subsequently declared the environmental review process complete in a record of decision issued on January 18, 2011.[28]
Native burials
[edit]Like most major infrastructure work in Hawaiʻi, construction of the rail line was likely to uncover historic human remains, notably in its downtown Honolulu section. The Oʻahu Island Burial Council (part of the State Historic Preservation Division, within the State of Hawaiʻi Department of Land and Natural Resources) refused to sign a programmatic agreement on October 21, 2009, over concerns about likely burial sites located along the line's proposed route over Halekauwila Street in Kakaʻako. Three construction projects in the area since 2002 have each encountered unforeseen human remains that led to delays, and archaeologist Thomas Dye stated, "The council is absolutely right that you should expect to find burials on Halekauwila Street".[29]
The Burial Council's core contention was the city's decision to conduct an archaeological survey of the rail line's route in phases, meaning construction on a majority of the line will be complete by the time the survey in the Kakaʻako area is performed, which in turn increases the likelihood that any remains discovered will be moved instead of being allowed to remain in situ.[30] In response to the Burial Council's concerns, the city agreed to begin conducting an archaeological survey of the area in 2010, two years earlier than originally planned.[29] The state Department of Land and Natural Resources later signed the city's programmatic agreement on January 15, 2011, over the continuing concerns of the Burial Council.[31]
The city's decision to conduct the archaeological survey in phases subsequently led to a lawsuit filed on February 1, 2011, by the Native Hawaiian Legal Corporation on behalf of cultural practitioner Paulette Kaleikini. The suit, which named both the city and the State of Hawaiʻi as defendants, contended that state law requires the full length of the rail line to have an archaeological survey conducted before any construction takes place, and seeks to void the environmental impact statement and all construction permits issued for the project.[32] Kaleikini's lawyers filed on February 18 a request for an injunction to stop work on the project until the case is resolved.[10] The suit was initially dismissed on March 23, 2011, after Circuit Court Judge Gary Chang ruled that state and federal laws allow the archaeological surveys to be conducted in phases.[33] Kaleikini's lawyers subsequently appealed to the Hawaiʻi Supreme Court, which heard oral arguments in the case on May 24, 2012.[34] The court ruled on August 24, 2012, that it agreed with plaintiff Kaleikini that the archaeological survey needed to be completed before construction could take place, and that the State Historic Preservation Division did not comply with state law when it approved the project. The case has now been remanded to Circuit Court.[35] On December 27, 2012, the United States District Court for the District of Hawaii granted the plaintiffs' injunction, and ordered that all construction-related activities in segment 4 of the archaeological survey be halted until compliance with the Hawaiʻi Supreme Court decision made earlier this year is met. This ruling does not affect construction activities in the first three segments, nor does it affect construction planning, design, or engineering in segment 4, which is the final segment to be built. The Phase 4 area encompasses the downtown area and its immediate environs, including Chinatown, Mother Waldron Park, and Beretania Street. Judge Tashima, the only sitting judge on the case, ruled on condition of the injunction that the city is required to file periodic status updates on their compliance with the judgment. The injunction will then terminate 30 days after defendants file a notice of final compliance.[36]
Impact on Honolulu mayoral elections
[edit]The importance of the Honolulu High-Capacity Transit Corridor Project in the 2008 mayoral election led one observer to describe the vote as a "referendum on rail transit".[6] Two challengers emerged as rivals to incumbent Mufi Hannemann: City Councilmember Ann Kobayashi and University of Hawaiʻi professor Panos D. Prevedouros. Kobayashi supported a "rubber-tired" mass transit system, as opposed to the conventional system chosen by the Hannemann administration. Prevedouros, on the other hand, opposed any type of mass-transit project, favoring construction of a reversible tollway over the H-1, similar to the Managed Lane option which the Alternatives Analysis studied and rejected as unworkable, and reworking existing road systems to ease congestion.[37] No candidate won a majority of votes in the September 20 primary, forcing a runoff between Hannemann and Kobayashi;[38] Hannemann successfully retained his post with 58% of the vote in the November 4 general election.[39]
On April 22, 2008, the Stop Rail Now advocacy group announced their intent to file a petition with the city to place a question on the 2008 ballot to create an ordinance that read: "Honolulu mass transit shall not include trains or rail".[40] Stop Rail Now attempted to submit the petition with 49,041 signatures on August 5, but was initially denied after the city clerk claimed the city charter did not allow the petition to be submitted less than 180 days before a general election, as the wording of the petition called for a special election.[41][42] The group filed a lawsuit to force the city to accept the petition, and the courts ruled in Stop Rail Now's favor on August 14.[43] Stop Rail Now's effort ultimately failed on September 4 when the city clerk deemed only 35,056 of the signatures valid, well short of the 44,525 required.[44]
In response to the possibility that Stop Rail Now's petition would fail, the City Council had however voted on August 21 to place a proposed amendment to the city charter on the ballot, asking voters to decide the fate of the project.[45] Mayor Hannemann signed the proposal the following day.[46] The City Council's proposed amendment was not intended to have a direct legal effect on the city's ability to continue the project, but was meant as a means for Oahu residents to express their opinions on its construction.[7] The charter amendment was approved with 53% of votes cast in favor of rail and 47% against. Majorities of voters in Leeward and Central Oahu, the areas that will be served by the project, voted in favor of the amendment, while the majority of those living outside the project's scope in Windward Oahu and East Honolulu voted against it.[8] In mid-2010, Hannemann resigned as mayor to run for governor and Kirk Caldwell assumed the position of interim mayor.[47]
In the 2016 Honolulu mayoral election the main three candidates again took opposing views on rail. Honolulu City Council Member Charles Djou, former mayor Peter Carlisle, and incumbent Kirk Caldwell all ran with the stated goal of finishing rail. However, Republican Djou ran on drastically cutting spending on rail by cutting funding on buying cars on the rail before its completion and hiring mainland consultants.[48] Caldwell also stated that spending on rail should be cut, but instead by shortening the rail to end at Middle Street.[49] Carlisle was the only candidate in support of funding the full rail system and stated that rail has gone too far to be stopped.[50] Caldwell won the election, and promptly went on to adopt Carlisle's position that rail should be completed.
Delays and cost overruns
[edit]Construction on the rail line was originally scheduled to begin in December 2009 but did not occur due to delays in the project review process and delays in obtaining federal approval of the environmental impact statement.[51]
In January 2010, Republican Governor Linda Lingle publicly recommended that the city alter plans for the rail line after news reports on FTA documents where the federal agency raised issues over declining tax revenues in connection with a global economic recession,[52] and commissioned a study by the state to review the project's finances in March.[53] The state financial study, publicly released on December 2, 2010, indicated that the project would likely experience a $1.7 billion overrun above the $5.3 billion projected cost, and that collections from the General Excise Tax would be 30% below forecasts. Then Mayor Peter Carlisle (Democrat) dismissed the study as "damaged goods," and "a pre-determined anti-rail rant." He also pointed to several conclusions as "erroneous" and "inaccurate" before concluding that "spending a third of a million dollars for this shoddy, biased analysis is an appalling waste of our tax dollars."[54] Lingle's Democratic successor, Neil Abercrombie, publicly stated that the financial analysis would not affect his decision to approve or disapprove of the project, saying that the state's responsibility is limited to the environmental review process, and that decisions regarding the project's finances belong to the city and the FTA.[55] Governor Abercrombie subsequently approved the project's final environmental impact statement on December 16, 2010.[56] The Honolulu City Council held a hearing on January 12, 2011, about the state's financial review, but the hearing was not attended by any state officials, who had been invited to testify.[57]
On January 18, 2011, the FTA issued a "record of decision", indicating that the project had met the requirements of its environmental review and that the city was allowed to begin construction work on the project.[28] The record of decision allowed the city to begin negotiating with owners of land that will be purchased for the project, to begin relocating utility lines to make way for construction of the line and stations, and to purchase rolling stock for the rail line.[58][59] A ground-breaking ceremony was held on February 22, 2011, in Kapolei, at the site of the future East Kapolei station along Kualakai Parkway.[9][10]
The City and County of Honolulu established the Honolulu Authority for Rapid Transportation (HART) on July 1, 2011. HART is a semi-autonomous government agency authorized to develop, operate, maintain, and expand the rail system. HART is led by its own Board of Directors, which appoints an Executive Director/CEO to provide leadership, direction and supervision of the day-to-day business activities of the agency.[60][61]
In March 2012, Dan Grabauskas was hired on a three-year contract as the first Executive Director/CEO of HART.[62] In 2014 HART CEO Dan Grabauskas blamed lawsuits, launched in 2011, for some of the cost overruns after bids to construct the first nine stations exceeded the budget by $100 million. His claims were disputed by the plaintiffs in one of the cases, who said HART could have put the stations out to tender and that HART had deliberately delayed the legal proceedings so a judgment would only be delivered after a significant proportion of the line had been completed.[63]
Testing and more delays
[edit]Interim service over the first ten miles of the line, between East Kapolei and Aloha Stadium, was scheduled to commence in October 2020. However, complications due to the COVID-19 pandemic pushed the start date back by three months.[64][65] By November 2020, the opening had again slipped to late 2021 due to delays in testing equipment.[66]
In December 2020, HART discovered early wear on the track crossings, or "frogs". It was later determined that the trains' wheel flanges were approximately one-half inch (13 mm) narrower at the frogs, thus affecting the driverless trains' ability to safely navigate certain track crossings at the speeds needed to operate on schedule. During investigation, subpar welding and sandblasting-induced cracks were also discovered.[67][68] In November 2021, Roger Morton, director of Honolulu's Department of Transportation Services, stated that a required three months of field testing and certification (to be carried out by Hitachi) was scheduled to begin in January 2022.[69]
In December 2021, it was decided that temporary welding fixes would be made to allow the trains to run at operational speeds despite the narrower wheels, with plans to swap out wheels with wider ones during future maintenance work. An initial call searching for contractors to perform the manganese welding work failed to return any bids.[70] Due to the lack of local companies able to complete the work, the state's Department of Commerce and Consumer Affairs granted HART an exemption allowing mainland contractors to be hired.[71]
Social impact
[edit]Proponents of the system say it will alleviate worsening traffic congestion, already among the worst in the United States.[72][73] They assert that the urban agglomeration in south Oʻahu is ideally suited to rail. In opposition, freeway advocate Panos Prevedouros has questioned its cost-effectiveness compared to "road widening or lane addition",[72] and believes it will have marginal impact on traffic congestion, despite research showing that widening highways results in induced demand and does not fix traffic.[74][75]
Financing
[edit]Construction of Skyline is financed by a surcharge on local taxes as well as a $1.55 billion grant from the Federal Transit Administration (FTA). After major cost overruns, the tax surcharges were extended in 2016 by five years to raise another $1.2 billion; however that additional funding was only sufficient for construction out to Middle Street in Kalihi. The FTA stated that its contribution is contingent to completion of the line all the way to Ala Moana Center, and will not be increased.[76] After much wrangling, the state legislature in 2017 approved $2.4 billion in additional taxes to allow the city to complete the project according to the original plan.[77]
The process to award the contract for building the final 4.3-mile (6.9 km) section through downtown Honolulu was suspended in 2015. The process was restarted in September 2017,[78] and the first major contract for that section, estimated at $400 million, was awarded in May 2018.[79]
The final cost has grown from preliminary projections of $4 billion in 2006[80] to as much as $12.4 billion by 2021.[81] Critics have called for a "forensic audit" to establish the cause of the increase.[82][83][84] The tax increase legislation passed in 2017 also requires the State auditor carry out an audit of the project's accounts[85] and to consider alternatives for completing the system.[86] The projected shortfall for the rail project is roughly $3 billion, with the completion date pushed back to 2031.[87]
Initial General Excise Tax (GET) surcharge
[edit]After winning the 2004 election, Hannemann announced that construction of a rail line was an administration priority.[88] The following May and upon prompting by the city, the Hawaii State Legislature passed a bill (Act 247) to allow counties a one-half percent increase in the Hawaiʻi General Excise Tax (GET), from 4% to 4.5%, to fund transportation projects. According to the bill, increased revenue would be delivered to counties implementing the raised tax to fund general public transportation infrastructure throughout Hawaiʻi, and to pay for mass transit in the case of the City and County of Honolulu.[89][90] Money collected from the initial 4% GET would remain state revenue.
Republican governor Linda Lingle initially threatened to veto the bill, believing that money destined for county governments should be collected by the individual counties.[91][92] After compromising with legislative leaders and Mayor Hannemann, however, she allowed the bill to become law. On July 12, 2005, the bill was enacted as Act 247 of the Session Laws of Hawaiʻi 2005, without the Governor's signature.[90][91][92][93] A month later, the Honolulu City Council authorized the one-half percent GET increase,[94] and Hannemann signed the measure into law on August 24.[95] Act 247 required Honolulu to use the funds only for the construction and operation of a mass transit system, and barred its use for public roads and other existing transit systems, such as TheBus. Since no other county authorized the excise tax increase before the deadline of December 31, 2005, the Hawaiʻi GET remains at 4% for the state's three other counties.[90][96] The increase went into effect on January 1, 2007, and was due to expire on December 31, 2022.[90]
The Legislature considered a bill in the 2009 legislative session that would have redirected income from the half-percent increase back to the state to offset a $1.8 billion projected shortfall in the following three fiscal years.[97][98][99][100] The bill was opposed by Mayor Hannemann and other city leaders who believed that redirecting the money would jeopardize federal funding for the project,[101] and was eventually dropped after U.S. Senator Daniel Inouye indicated to the Legislature that he shared the city's concerns.[102][103]
GET surcharge extensions and "Hotel Tax" surcharge
[edit]In January 2016, the Council extended the GET for another five years to add $1.2 billion in funding to cover a budget blowout. The council also required that the money raised by the extension go into a contingency fund and to pay for disability access to the system. HART was required to provide quarterly financial reports to the council.[104]
On September 1, 2017, the Legislature, after meeting for a week in a special session on rail financing, approved further taxes to raise $2.4 billion for the project. The taxes include a further three-year extension to the 0.5 percent General Excise Tax surcharge, which will now expire in 2030, and a thirteen-year, one percent surcharge on the existing 9.25 percent statewide Transient Accommodation Tax (TAT) which is charged to hotel guests. Efforts to pass a funding bill in May 2017 had failed and the impetus for the special session was an FTA deadline of September 15 for a funding plan to cover the shortfall.[105] The bill also grants the state government oversight over the project including the appointment of two non-voting representatives on the HART board and calls for an audit of HART by the state auditor. It was signed into law by the governor on September 5.[85]
Federal Transit Administration's request for recovery plan
[edit]In mid 2016, the FTA requested that HART develop a "recovery plan" by August 7, 2016. Also, in June, a separate report by Jacobs Engineering, the project management contractor, said under a worst-case scenario the final cost would be $10.79 billion.[106]
In January 2017, a group called "Salvage the Rail" published a plan, based on Option 2A from six alternatives proposed by the FTA to HART in 2016,[107] that would terminate the elevated section at Middle Street and run at street level to the terminus along a route one block inland from the HART plan. The system would need to be reconfigured to use new driver-operated low floor vehicles, lowering the platforms on the stations already constructed.[108][109] Proponents say it would save $3 billion and four years of construction, as well as avoid disturbing burial sites under the downtown area.
After an extension was granted by the FTA, HART submitted its recovery plan in April 2017 which concluded that completion of the original 21 station route was the only viable option. An alternative "Plan B" to build only 14 stations within the already funded $6.5 billion budget, was ruled out because of lower ridership, legal risks, insufficient contingency and other reasons. The new project cost was $8.165 billion with media reports indicating that after financing charges are included it could be over $10 billion. An updated schedule for opening said the section from East Kapolei to Aloha Stadium will open at the end of 2020 and operation of the full route by December 2025.[110][111]
In September 2017, HART submitted an updated recovery plan to the FTA with a new estimate price of $9.02 billion. The plan still includes $8.165 billion in construction costs, but has reduced financing costs of $858 million following state legislation granting both prolonged and new taxes to fund the project.[112] The State Auditor has been tasked to consider alternatives for completing the system, as part of its audit of HART.[86] As of January 2018 the FTA has not formally accepted the new recovery plan but has asked HART for more details including how it came up with its tax-revenue forecasts.[113]
In February 2019, the FTA served HART with two subpoenas. The first asked the agency to send investigators documents relating to its real estate acquisition program. HART said some of the documents show it overspent on relocating residents and businesses along the rail route, which may have cost up to $4 million.[114] The second sought the minutes from all board of directors meetings from 2011 through 2018, including the board-members’ private discussions in executive sessions.[115]
In September 2019, the FTA accepted the recovery plan.[116]
Revised schedule and estimates
[edit]An estimate released in November 2020 put the total cost of the project's construction and financing at $11 billion, and pushed back its expected completion date to 2033, with delays due to the COVID-19 pandemic and utility relocation work.[117] By March 2021, this had grown to $12.4 billion, with its estimated completion date moved forward to March 2031.[118][119] Its construction constitutes Hawaiʻi's largest public works project ever.[120]
Route
[edit]Skyline consists of an almost entirely elevated rapid transit line from the eastern edge of Kapolei, near the University of Hawaiʻi–West Oʻahu campus, to the Hawaii Capital Historic District, with a future expansion planned to Ala Moana Center (east of downtown Honolulu). It will have twenty-one stations and run from Kapolei to Honolulu on the southern shore of Oʻahu, passing through Waipahu, Pearl City, Waimalu, Aiea, and Halawa. The only at-grade trackage is a 0.6-mile (0.97 km) section near Leeward Community College, but has no grade crossings.[121]
The full project is divided into four sections with overlapping construction periods and expected revenue service dates:[122][123]
- In 2016, the western portion of the line comprising the first segment (Kualakaʻi to Hālawa) was scheduled to open in late 2020, and the remaining portion and final three segments (Hālawa to Kālia) in late 2025.[124] In March 2021, this latter date was pushed back to 2031.[125] On May 9, 2023, it was announced that the first segment would open the following month on June 30.[126]
- The project also anticipates opening the second segment of service from Hālawa to Kahauiki in late 2025, ahead of the previously estimated date of 2031.[119][126] Originally announced to open in the summer, on May 14, 2024, it was announced the opening of this segment would be pushed to late 2025.[127][123]
- The third segment from Kahauiki to Kaʻākaukukui is still expected to open in 2031.
- The final two stations between Kaʻākaukukui and Kālia have been indefinitely deferred, although HART says it remains committed to completing them in the future.[128]
Segment | Length | Termini | Opening | Ref. | |
---|---|---|---|---|---|
1 | 10.8 miles (17.4 km) | Kualakaʻi | Hālawa | June 30, 2023 | [129] |
2 | 5.3 miles (8.5 km) | Hālawa | Kahauiki | Late 2025 (scheduled) | [119][125][130] |
3 | 3.3 miles (5.3 km) | Kahauiki | Kaʻākaukukui | 2031 (scheduled) | [119][125][131] |
Ala Moana extension | 0.8 miles (1.3 km) | Kaʻākaukukui | Kālia | — | [132] |
Design
[edit]Segment 1: Farrington/Kamehameha
[edit]On October 21, 2009, the city announced Kiewit Pacific Co. had won the $483 million contract to build the first phase of the line (the 7-mile (11 km) long Farrington and 4-mile (6.4 km) long Kamehameha sections), bidding $90 million under the expected price. The stations were tendered separately.[133][134]
The construction of the rail line started from suburban areas in Kapolei and Ewa, and progresses east towards the urban center in Honolulu. There are 112 columns from Kualakaʻi station to the ʻEwa area.[135] The choice to start from Kapolei was made because the first phase must include a baseyard for trains, which is more cheaply built away from the center, and also because the city chose to delay construction in the urban center to later phases of the project due to associated major impacts to existing infrastructure and unpopular traffic delays.[136]
To speed construction, the elevated trackway is built using precast concrete box girder bridge segments.[137] This method was first used for MARTA in the 1980s.[138] The trackway was designed by FIGG Bridge Engineers (responsible for the box girder segmental bridge) and HNTB (responsible for the columns). It is supported on single piers, each 6 to 7 feet (1.8 to 2.1 m) in diameter at the base and 30 feet (9.1 m) high, flaring at the top to support the lower section of the box girder; the piers are themselves supported by drilled shafts from 7 to 8 feet (2.1 to 2.4 m) in diameter.[137]
Casting of the box girder segments began in 2014 at a rate of 13 segments per day; in total, 5,238 segments will be required for the first 10 mi (16 km) phase.[139] The segments are cast locally in Kalaeloa.[140] Each segment weighs 100,000 pounds (45,000 kg) and measures (L×W×H, with length measured along the direction of the rails) 11 by 30 by 7 feet (3.4 m × 9.1 m × 2.1 m),[141] and the deck ranges in thickness from 8 to 15 inches (200 to 380 mm).[137] Once the piers were erected, a pier bracket ram was placed and a launching gantry was used to bridge the span between adjacent piers; a deck-mounted crane lifted the precast segments onto the gantry, which supported them while they were tensioned together.[142] In total, 430 of the 438 spans in Phase 1 were assembled using precast box girder segments, at an average rate of 1 to 2 days per span.[137]
For the eight long spans required to bridge the H-1/H-2 Waiawa interchange in Pearl City, a balanced cantilever construction method was used instead. This covers the segments from Pier 252 to Pier 256.[141] Instead of precast segments, Kiewit used segments cast in-place, starting from the piers set in the freeway medians and working towards adjacent piers. The yellow-painted traveling forms at each end were used to cast each segment, then moved to the fresh end to cast the next segment. Each segment required 8,000 pounds (3,600 kg) of rebar and 48 cubic yards (37 m3) of concrete, and weighed 210,000 lb (95,000 kg). 73 segments were required.[143] The final pour for the balanced cantilever was performed in September 2016.[144]
-
Kamehameha Highway section under construction (2017), viewed east towards Aloha Stadium
-
Precast bridge segments supported by cylindrical piers were used to construct most of the guideway (2015)
-
Balanced cantilever construction over Interstate H-1 in 2015
Segment 2: Airport
[edit]The second phase of the route to be completed will be the 5.1 mi (8.2 km) Airport section east from Aloha Stadium to Middle Street (the site of Kalihi Transit Center, an existing major bus transfer point). It includes four stations, including the Honolulu International Airport station. AECOM won the contract to design the Airport section in 2012 with a $38.8 million bid.[145] The construction contract was awarded to the Shimmick-Traylor-Granite Joint Venture (STGJV) in August 2016, who bid $874.8 million;[146][147] construction started in December 2016.[148]
Originally, the line was to fork near Aloha Stadium into two routes, one passing further south via Honolulu International Airport, and the other through Salt Lake, before reuniting at Middle Street in Kalihi. The city council initially decided to build the Salt Lake route before the airport route, as a result of horse-trading with City Councilmember Romy Cachola, whose constituents included Salt Lake residents and whose vote was needed to pass the decision.[149][150] After the city charter amendment on rail transit passed, the City Council reconsidered the decision, and decided to re-route the rail line to pass by Pearl Harbor and the airport and shelving the Salt Lake alignment as an future extension.[151][152] Despite increasing expenses by 4%, the airport route is expected to bring significantly higher ridership, as it will ferry workers to both the airport and the Pearl Harbor military base.
The Airport section consists of 214 total spans. Like the earlier Farrington and Kamehameha sections, they are constructed using precast concrete box girder bridge segments, but for the Airport section, the segments are lifted and supported by an overhead gantry crane while they are tensioned.[153] Both a conventional overhead gantry and an articulating gantry are being used during the guideway assembly.[154] More than 2,700 precast segments are required for the Airport section, which also includes more than 230 columns for the piers and 5400 permanent sound walls. For the pier foundations, shafts were drilled up to 350 feet (110 m) deep,[155] including one excavated to 357 feet 4 inches (108.92 m) with a diameter of 10 feet (3.0 m). This was believed to have established a new record for a drilled shaft caisson. The column, in Kalihi Stream on Kamehameha Highway between Middle Street and Puʻuhale Road, will be part of the support for Kahauiki station.[156] Where the guideway contacts the supporting piers, custom bearings have been installed to accommodate movement ranging from 2 to 19 inches (51 to 483 mm) and rotation of 0.015–0.03 radians.[157]
STGJV announced in December 2020 it had completed the last of the 2,708 precast concrete guideway segments for the Airport section, with this last segment scheduled to be installed over Ualena Street near Lagoon Drive in spring 2021. Each segment uses approximately 18 cu yd (14 m3) of concrete. Finished segment weights vary between 80,000 to 130,000 lb (36,000 to 59,000 kg) and have dimensions of 30.5 feet (9.3 m) wide, 10.75 feet (3.28 m) long, and either 8.5 or 4.5 feet (2.6 or 1.4 m) high. The lower height is used in several places along the Airport section to accommodate overhead clearances and flight path restrictions.[158]
Segment 3: City Center
[edit]The third phase of the route to be completed will be the 3.3 mi (5.3 km) City Center section east from Kahauiki (Middle Street) station to Kaʻākaukukui (Civic Center) station. It includes six stations, including a downtown station. In August 2024, Parsons and Tutor Perini who bid $1.66 billion; won bids for design and construction for the city center section respectively. Design works have started and construction will start in the second half of 2025.[159][160]
Originally the 3.3 mi (5.3 km) section terminating at Kaʻākaukukui station, was supposed to be completed under a public-private partnership (PPP). It was estimated the City Center section will cost $1.6 billion to complete.[161] Under the proposed PPP, the City Center section would be procured under a design-build-finance-operate-maintain (DBFOM) contract, which would award the successful bidder the right to operate and maintain the entire system for a period of 25 years after completing the City Center section. The City of Honolulu would retain oversight over operations and maintenance, public information, and responsibility for fare vending and enforcement.[162] A contract for $400 million to clear utilities in the City Center section was awarded in May 2018.[79]
HART issued a request for proposals (RFP) for the DBFOM contract for the City Center Guideway and Stations section in late 2018[163] and announced it had received proposals from several bidders by July 2020.[164] However, the bids for the construction of the City Center Guideway and Stations significantly exceeded HART's cost estimates, at $2.7 billion compared to the $1.4 billion estimate,[165] and HART officially discontinued pursuing a PPP approach to completing the City Center section in November 2020.[166] The bids for the operation and maintenance portion of the contract (ranging from $4.2 to $5.3 billion) were closer to the estimate ($4.95 billion).[165] On December 14, 2020, HART issued a request for information, asking for input from the construction industry for the best way to structure a RFP that would receive realistic bids. It was expected that this contract will be awarded and subsequently, construction will begin for the six stations and guideway in August 2024.[167]
In 2021, due to rising costs regarding the complexity of the City Center utility relocations; the original $400 million contract for clearing utilities signed back in 2018 was terminated and this section of utility relocations was divided into two contracts, one for utility relocations on Dillingham Blvd between Kahauiki station and Kūwili station as well as another for the city center between Kūwili station and Kaʻākaukukui station. In addition to this, the utility relocations were significantly rescoped to save costs.[168][169]
The significantly re-scoped utility relocations required modifying the original alignment. This culminated in changes from various column changes to re-routing the guideway with the "Mauka Shift" alignment where the sheer amount of utilities on the southern half of Dillingham Boulevard between Waiakamilo and Kaaahi streets resulted in the alignment changed from being in a median strip to being on the northern shoulder of the roadway. Subsequently, the Niuhelewai station in this stretch will be redesigned to reflect this shift.[170][171]
Ala Moana extension
[edit]Kūkuluaeʻo (Kakaʻako) and Kālia (Ala Moana Center) stations were included in the original plan for Skyline but had to be eliminated from the initial phases of construction due to a severe funding shortfall. Despite the indefinite deferral, the Honolulu Authority for Rapid Transportation says it remains committed to completing these stations in the future. In 2024, Tutor Perini has offered to do this section as a $325 million "add on" project to its city center construction contract after winning the bid for the rail construction between Middle Street and Civic Center.[172][128]
Potential future extensions
[edit]The long-term plan includes four additional extensions beyond Kualaka'i (East Kapolei) and Kālia (Ala Moana Center). These include extensions to University of Hawaiʻi at Mānoa, Waikīkī, Kalaeloa, and the link through Salt Lake which was dropped from initial plans. None of these extensions are currently funded, but steps are being done in preserving alignments; especially in regards to ongoing projects planned on these alignments.[173][133][174]
Extensions past Kālia (Ala Moana)
[edit]Past Kālia (Ala Moana), the alignment than travels to the Hawaii Convention Center with a station then it splits into two branches, one to the University of Hawaiʻi at Mānoa campus and the other to Waikīkī on Kuhio Avenue.
In November 2017, the rail authority took a first step towards preserving a corridor for the extension to the University of Hawaiʻi at Mānoa.[175]
In 2023, The City and County of Honolulu has started preserving the Waikiki Alignment by installing Bus Lanes on Kuhio Avenue that could eventually be used for the future rail alignment's columns in addition to a future transit-only Kuhio Avenue.[176]
In 2023, The City and County of Honolulu has started preserving the U.H Manoa Alignment by installing bike lanes on University Avenue that could eventually be used for the future rail alignment's utility relocations and columns such as a possible Mauka-Shift style movement between the Moilili and UH Manoa Stations being considered for in this project.[177]
Extensions past Kualakaʻi (East Kapolei)
[edit]In addition to this; one extension is planned west from Kualakaʻi (East Kapolei) to Kalaeloa.
In 2021, The City and County of Honolulu has started planning to move the Kapolei Transit Center closer to the future Kalaeloa alignment.[178][179]
Salt Lake extension
[edit]The link through Salt Lake between Hālawa (Aloha Stadium) and Kahauiki (Middle Street) which was dropped from initial plans is being planned as an extension.
On April 29, 2021, Phase 3 of the Salt Lake Boulevard Widening Project commenced. This is upgrading the final 2-lane part of Salt Lake Boulevard to 4 lanes. In addition to this, this project also makes this part of the Salt Lake corridor compatible for the future Salt Lake extension.[180]
Operations
[edit]Stations
[edit]Local construction company Nan, Inc. won contracts to build six of the nine western stations in 2015; the West Oahu Station Group contract (for Kualakaʻi, Keoneʻae, and Honouliuli) was worth $56.1 million,[181] and the Kamehameha Highway contract (for Waiawa, Kalauao, and Hālawa) was worth $116 million.[182] The Farrington Highway Station Group contract (for Hōʻaeʻae, Pouhala, and Hālaulani) was awarded in 2015 to Hawaiian Dredging for $79 million.[183] STGJV was awarded the contract to build the four Airport section stations (Makalapa, Lelepaua, Āhua, and Kahauiki) as part of their $875 million contract.[184]
The Hawaiian Station Naming Working Group (HSNWG) was named by the Honolulu City Council in 2009 to develop Hawaiian names for each Skyline station.[185] HSNWG proposed Hawaiian names for the nine rail stations on the ʻEwa end of the rail system in November 2017, and HART adopted the proposed names in February 2018.[186][187] In April 2019, HSNWG recommended its names for the remaining 12 rail stations on the eastern end of the rail system, between Pearl Harbor and Ala Moana Center.[188][189]
All stations have restrooms that riders must ask a station attendant to unlock before using. They are described as being "secured access", in order to deter vandalism and improve the safety and security of stations, yet are "available for the public."[190]
List of stations
[edit]# | Name[191][192] | Location | Segment[122][193] | Opening | Notes | |
---|---|---|---|---|---|---|
Hawaiian | English | |||||
1 | Kualakaʻi | East Kapolei | East Kapolei | Segment 1 10.8 mi 17.4 km |
June 30, 2023 | Serves Kapolei, Makakilo, Kalaeloa,ʻEwa, Ka Makana Alii Shopping Center, Kapolei Kroc Center and ʻEwa Beach |
2 | Keoneʻae | University of Hawaiʻi – West Oʻahu | Serves the University of Hawaiʻi – West Oʻahu campus and Honouliuli Park and ride: 304 spaces | |||
3 | Honouliuli | Hoʻopili | Serves Honouliuli Park and ride: 344 spaces | |||
4 | Hōʻaeʻae | West Loch | Waipahu | Serves West Loch, ʻEwa, ʻEwa Beach, Kunia and Waipahu Park and ride: 21 spaces (temporary lot) | ||
5 | Pouhala | Waipahu Transit Center | Serves Waipahu and Waikele | |||
6 | Hālaulani | Leeward Community College | Pearl City | Serves Leeward Community College, Pearl City and Waikele | ||
7 | Waiawa | Pearl Highlands | Serves Pearl Highlands, the Pearl Highlands Center, and Pearl City | |||
8 | Kalauao | Pearlridge | Waimalu | Serves the Pearlridge Center, Pearl City, Waimalu, and ʻAiea Park and ride: 16 spaces (temporary lot) | ||
9 | Hālawa | Aloha Stadium | Hālawa | Serves Aloha Stadium, ʻAiea, Salt Lake, Ford Island, Pearl Harbor Memorial, Pearl Harbor, and Moanalua Park and ride: 590 spaces | ||
10 | Makalapa | Joint Base Pearl Harbor–Hickam | Honolulu | Segment 2 5.1 mi 8.2 km |
Late 2025 (scheduled) |
Serves Joint Base Pearl Harbor–Hickam, Moanalua and Salt Lake |
11 | Lelepaua | Daniel K. Inouye International Airport | Serves Daniel K. Inouye International Airport, Moanalua, and Salt Lake | |||
12 | Āhua | Lagoon Drive | Serves Lagoon Drive, Moanalua, Keehi Lagoon Park and Mapunapuna | |||
13 | Kahauiki | Middle Street–Kalihi Transit Center | Serves Kalihi, Fort Shafter, Moanalua, Sand Island, and Honolulu Harbor | |||
14 | Mokauea | Kalihi | Segment 3 3.3 mi 5.3 km |
2031 (scheduled) |
Serves Kalihi, Bishop Museum, and Honolulu Harbor | |
15 | Niuhelewai | Honolulu Community College–Kapalāma | Serves Kalihi, Kapālama, Honolulu Harbor and Honolulu Community College | |||
16 | Kūwili | Iwilei | Serves Iwilei, Kalihi, Nuuanu, Honolulu Harbor, Kuakini, and Liliha | |||
17 | Hōlau | Chinatown | Serves Chinatown, Nuuanu, Hawaii Theatre, and Honolulu Harbor | |||
18 | Kuloloia | Downtown | Serves Downtown Honolulu, Aloha Tower, Honolulu Harbor, Honolulu Harbor Cruise Terminals, and the Capital District | |||
19 | Kaʻākaukukui | Civic Center | Serves Kakaʻako, Kaka'ako Waterfront Park, Our Kakaʻako, Punchbowl, Capital District, Ward Village, Alapai Transit Center, The Queen's Medical Center, and the University of Hawaiʻi Cancer Center | |||
20 | Kūkuluaeʻo | Kakaʻako | Ala Moana extension 0.8 mi 1.3 km |
TBD | Serves Ward Village, Kakaʻako, Ala Moana Beach Park, Honolulu Museum of Art, McKinley High School, Straub Medical Center, and the Neal S. Blaisdell Center. | |
21 | Kālia | Ala Moana Center | Serves Ala Moana, the Ala Moana Center, Ala Moana Beach Park, McCully, Hawaii Convention Center, Kaheka, Makiki, Mānoa, and Waikīkī |
Ridership
[edit]When fully complete, Skyline trains are expected to carry more than 6,000 people per hour and operate between 4 a.m. and midnight.[194][124] Segment 1 is estimated to see 8,000 to 10,000 daily riders after one year of opening. The opening of Segment 2 (in 2025) will see this number grow to 25,000, and with Segment 3 (in 2031), Skyline is projected to have a daily ridership of 85,000.[195][196] Upon opening the extension to Ala Moana, Skyline will serve an estimated 119,600 daily riders.[197]
During its opening weekend, between 2 p.m. on Friday, June 30 and 7 p.m. on Sunday, July 2, 2023, Skyline saw 40,668 riders, equivalent to over 1,500 passengers per service hour.[198] During the first five days of service, which were fare-free, Skyline saw a total of nearly 72,000 passengers.[199]
In 2023, the line had a monthly ridership of 614,800,[200] or about 3,000 per weekday as of the second quarter of 2024.[201] The month of September 2024 saw a total of 103,735 riders, averaging 3,458 people per day, with an on-time performance rate of 99.6%.[202][203]
Fares
[edit]Stations are equipped with fare gates and ticket vending machines (TVMs). Fares may be purchased by passengers and loaded onto HOLO cards, which also facilitate transfers to TheBus, providing an unlimited number of free transfers for 2.5 hours after any boarding.[204] The base cost of a HOLO card without fare is $2.[205] TVMs interfaces are available in English, Hawaiian, Samoan, Tagalog, Ilocano, Japanese, Chinese, and Korean.[206]
Rail Operations Center
[edit]The Rail Operations Center (ROC; also known as the Maintenance and Storage Facility) is the 43-acre (17 ha) railyard, operations, and maintenance facility, located between the campuses of Leeward Community College and Waipahu High School, just west of Hālaulani station. The design has been awarded LEED Silver certification.[207]
The four buildings on the ROC campus are:
- Operation & Servicing Building (OSB) – Housing primary vehicle maintenance facilities and the Operations and Control Center, where operators will monitor and control vehicle movement
- Maintenance of Way Building (MOW) – Housing equipment used to inspect and repair tracks
- Train Wash Facility (TWF) – An automated facility to clean vehicle exteriors
- Wheel Truing Building (WTB) – A maintenance facility for vehicle wheels
The contract for the ROC was awarded to the Kiewit/Kobayashi Joint Venture in 2011.[208] The contract was initially awarded at a cost of $195 million; when the ROC was completed in July 2016, the actual incurred costs were $274 million.[209]: 39
Rolling stock
[edit]Although several other technologies were considered, including rubber tires, maglev and monorail, then-mayor Mufi Hannemann strongly believed in "steel on steel" construction, saying "I will not put this city in a position of financial disaster […] If it's not 'steel on steel,' I'll pull the plug."[210] The line uses 256 ft (78 m) four-car train sets, each with the capacity to carry nearly 800 passengers,[211] similar in weight to heavy rail systems elsewhere in the United States (such as the Chicago 'L' in Chicago, Illinois). Physically, the Honolulu system resembles light rapid transit systems such as Vancouver's SkyTrain, the Copenhagen Metro, and the Docklands Light Railway in London, but is legally classified as a heavy rail system.[212] The system is the first in the U.S. to feature platform gates in conjunction with driverless operation.[213] Rolling stock for the line includes 80 cars in 20 four-car train sets.[214] Each car is 64 ft (20 m) long, weighs 72,000 lb (33,000 kg), and has 36 seats with a listed total capacity of 195 people, and sits on standard-gauge (1,435 mm) rails.[215][211] The cars are powered by a third rail electrification system, delivering 750 V DC.[216]
Contract and delivery
[edit]The contract for railcars (named the Core Systems Design-Build-Operate-Maintain Services contract) was signed on November 28, 2011, with a joint venture between Hitachi Rail Italy (then known as AnsaldoBreda) and Hitachi Rail STS (then known as Ansaldo STS).[217] The companies previously collaborated on the construction and operation of vehicles for the Copenhagen Metro[218] and the Brescia Metro. Both companies were later purchased by Hitachi in 2015[219] and the Ansaldo Honolulu Joint Venture was renamed to Hitachi Rail Honolulu (HRH).
Under the $1.1 billion contract, HRH is responsible for designing and fabricating railcars ($574 million), pre-revenue testing to validate train performance ($167 million), and operations and maintenance (O&M) during the first five years of revenue service ($339 million). There is an option to continue O&M services for HART for an additional five years ($318 million).[217]
The two unsuccessful bidders for the railcar contract, Bombardier and Sumitomo, filed protests over the award.[220] Both protests were rejected during the administrative process, but Bombardier sought judicial review of their protest.[221] The decision against Bombardier's protest was affirmed by both the state Circuit Court and the Intermediate Court of Appeals.[222][223]
The first two cars arrived in Hawaiʻi in March 2016,[224][225] and the first train was unveiled to the public at the Rail Operations Center on May 2, 2016.[226] To meet "Buy America" requirements for federally-funded transit projects, the bodyshells are fabricated at the Hitachi Rail Italy plant in Reggio Calabria, Italy, then shipped to Hitachi Rail's plant in Pittsburg, California for final assembly.[224]
In December 2016, Hitachi Rail Italy reported defects were discovered in the welds in the extruded aluminum beams of twenty-seven car shells, four of which were already in Hawaiʻi. The manufacturer will fix the problems, but warned delivery may be delayed as production of new vehicles will be halted.[227] In March 2017, HART said they would meet the interim opening needs after repair of the defective cars and that full opening would not be affected.[228]
In May 2017, trains were towed on tracks in Honolulu for the first time, to check clearances.[229] Testing of trains under their own power commenced in October 2017.[230]
Timeline of progress
[edit]- February 2006 – A draft transportation plan includes $2.5 billion for a fixed-rail system between Kapolei and Mānoa.[231]
- June 2006 – Officials estimate the infrastructure construction cost at estimated at $3 billion, $200 million more than a previous estimate, for a 24-mile system. This does not include the cost of the trains.[80]
- January 2007 – The General Excise Tax (GET) within the City and County of Honolulu is increased by 0.5% with the extra funds earmarked for a mass transit system. The increase was set to expire on December 31, 2022.
- February 2007 – The City Council approves the Minimum Operating Segment from East Kapolei to Ala Moana Centre, via Salt Lake Boulevard.[111]
- October 2008 – The Draft Environmental Impact Statement (DEIS) is released to the public. The projected cost is $3.7 billion including $1 billion for contingencies.[232]
- November 2008 – Fifty-three percent of voters support measures to give the Honolulu City Council authority to proceed with "establishment of a steel wheel on steel rail transit system". The estimated cost is $4 billion.[233]
- January 2009 – The middle portion of the route between Aloha Stadium and Middle Street is amended to have stations at the Pearl Harbor Naval Base and the Honolulu Airport which had one of the original options. The previous route followed Salt Lake Boulevard.[152]
- June 2010 – The Final Environmental Impact Statement (FEIS) is released to the public. Estimated cost is $5.5 billion. Patronage by 2030 is projected to be 116,300 riders per day.[234][235]
- December 2010 – A report, commissioned by outgoing Governor Lingle, is released which warns the project could cost at least $1.7 billion more than the city's projected $5.5 billion price tag.[54]
- March 2012 – Dan Grabauskas becomes executive director and CEO of HART on a three-year contract. He takes his position in April 2012.[62][236]
- May 2012 – Construction workers started pouring concrete on the foundations that will hold the rail columns.[237]
- December 2012 – Honolulu City Council and the Federal Transit Authority (FTA) sign agreement for the project with a budget of $5.12 billion including $1.55 billion provided by the Federal Government. Full system revenue service is projected for January 31, 2020.[238]
- September 2014 – HART canceled the initial tender for the first nine stations after the bids were higher than budget. "The lowest bid by Nan, Inc. came in at $294.5 million, or $110 million more than the $184 million the transit authority had budgeted." The first trips on the railway are expected to be delayed, probably until 2018.[239]
- November 2015 – FTA withholds payment of a $250 million allotment until the council could show it had sufficient funding to complete the project.[240]
- January 2016 – Five year extension to the General Excise Tax surcharge adopted to add $1.2 billion in funding.[238]
- May 2016 – HART chairwoman Colleen Hanabusa shared a confidential document detailing budget estimates as of March 1, 2016, showing that the rail project is expected to cost $6.9 billion.[241]
- April 2016 – An audit of the project by the City criticized HART for using outdated financial figures and budgets, lack of documentation for "change orders", and warned the HART estimates of the cost overruns were unreliable.[242][243] HART officials disputed the audit's findings.
- May 2016 – The FTA revealed that they estimate the total cost as $8.1 billion for the 20 mi (32 km) line. In addition completion of the rail system would be delayed nearly five years until December 2024, versus HART's federal funding agreement stating that full line service from East Kapolei to Ala Moana Center would start in January 2020.[244]
- June 2016 – Report from Jacobs Engineering, the project management oversight contractor, says that under a worst-case scenario the final cost would $10.79 billion.[106]
- August 2016 – Dan Grabauskas resigns as CEO and executive director of HART but will be the official CEO until October 2016. From August until October, the Department of Transportation Service Director Mike Formby served as interim CEO.[236][245][246]
- October 2016 – Krishniah N. Murthy named interim CEO and executive director of HART and served in this position until December 2017.[247]
- April 2017 – HART sent a "Recovery Plan" to the FTA which concluded that completion of the original 21 station route was the only viable plan. The new project cost given is $8.165 billion with media reports indicating that after financing costs are included it will be over $10 billion. Opening of part of the system, from East Kapolei to Aloha Stadium, is scheduled for the end of 2020 with final completion of the full route by December 2025. The project is reported to be 36 percent complete as of March 2017.[110][111]
- July 2017 – Andrew Robbins named new CEO and executive director of HART at a base salary of $317,000, replacing interim CEO and Executive Director Krishniah N. Murthy in December 2017.[247][248]
- September 2017 – A new law is enacted to extend and increase taxes to raise an additional $2.4 billion for the project. The GET surcharge is extended by three years to 2030 (generating about $1 billion) and a surcharge of one percent is placed on the statewide hotel room tax for 13 years (generating $1.3 billion).[105][85] HART submits a new recovery plan to the FTA with an estimated final cost of $9.02 billion with savings attributed to reduced financing costs given the new taxes.[112]
- January 2020 – Andrew Robbins, executive director and CEO of the Honolulu Authority for Rapid Transportation, said the first 10 miles of the Honolulu rail system would be completed by December 2020 as predicted, and will also be ready to run passenger service between Kapolei and Aloha Stadium three months earlier, by October 20, 2020. Robbins said he was so confident of the new date that he was willing to stick his neck out.[249]
- May 2020 – "Completion of the first 10-mile segment of the line from East Kapolei to Aloha Stadium, originally scheduled for October, will be delayed by about eight weeks, according to Honolulu Authority for Rapid Transportation executive director Andrew Robbins... And the city, which had forecast opening the line to riders by December, has pushed that date back to next March."[250]
- June 2020 – "More recently, the FTA has been projecting the project would be finished in September 2026, and insisted that the city incorporate that later date into its 2019 rail 'recovery plan.'"[251]
- July 2020 – The city finally received much-anticipated proposals from private industry to finish the project's major remaining construction work and then run the system for its first 30 years. The bids won't be publicly released until the contract is awarded by unidentified officials.[252]
- September 2020 – One of the PPP bidders for the final city center segment from Middle Street to Ala Moana Center revealed themselves during a recent quarterly earnings call. Ronald Tutor, CEO of Tutor Perini, disclosed that his company is part of the Tutor Perini / Parsons joint venture for the final segment of Honolulu rail. While HART estimated that this last stretch would cost $1.4 billion, Tutor stated that his company's bid was “over $2 billion.”[253]
- October 2020 – “The estimated cost of rail has jumped once again, bringing the construction and interest tab to the $10 billion threshold. The mayor tells us it will probably grow more, and the shortfall to pay for it all now tops more than $1.2 billion.”[254]
- November 2020 – In an effort to keep $250 million in federal funding from lapsing at the end of the year, Mayor Kirk Caldwell bypassed HART CEO Andrew Robbins and sent a letter to the Federal Transit Authority requesting a one-year extension through the end of 2021. A rough outline of a plan included in the letter suggested a total cost of $11.2 billion including approximately $1 billion in financing costs, and a completion date of 2033.[255]
- December 2020 – HART received bids for the city center segment from two private-sector teams: $2.775 billion by City Center Connection Group and $2.73 billion by Imua Transit Honolulu, vs HART's budget of $1.4 billion.[256]
- March 2021 – Under new leadership, HART announces an updated, official completion date of 2031,[125] with revenue service on the initial segment from Kapolei to Aloha Stadium beginning by the end of 2022.[257]
- December 2021 – “The head of the Honolulu Authority for Rapid Transportation says next summer is the earliest the rail system could begin partial operations.” [258]
- April 2022 – HART announces tight gage and weld modifications have been completed, with final 90-day testing to begin in the summer.[259]
- June 2022 – "The Honolulu Authority for Rapid Transportation says it’s hopeful residents will be using trains by the end of the year – even as construction in the urban corridor continues."[260]
- August 2022 – HART begins the 90-day trial testing phase.[261]
- September 2022 – "The Federal Transit Administration has approved the Honolulu rail's financial recovery plan which outlines a truncated version of the rail line, 1.25 miles short of Ala Moana Center."[132]
- May 2023 – Honolulu Mayor Rick Blangiardi and the Department of Transportation Services announces that Phase 1, which is the first nine stations that connect East Kapolei to Aloha Stadium, will open to the public at 2 p.m. on June 30, 2023, and that the next phase, which adds the Airport Extension that connects Aloha Stadium with four additional stations to Middle Street–Kalihi Transit Center station, will open in the summer of 2025. It was also announced that the final phase, which adds the City Center Extension with six stations, connecting Middle Street–Kalihi Transit Center to Civic Center, will open in 2031.[262][263]
- June 2023 – Skyline Phase 1 begins operations. The "Skyline" name is announced two weeks before opening,[264][265] inspired by the Hawaiian manu-o-Kū.[266]
- June 2024 – Electrification of Phase 2 begins. The service operation date is revised from summer 2025 to late 2025.[127][123]
In popular culture
[edit]- In the 2014 American film Godzilla, the MUTO monster attacks and destroys a train and a viaduct of the Skyline, which was actually under construction at the time.[267][268]
References
[edit]- ^ Vantuono, William C. (June 30, 2023). "'Skyline' Opens in Honolulu". Railway Age. Retrieved July 17, 2024.
- ^ "TP -1: Core Systems Description Honolulu High -Capacity Transit Corridor Project" (PDF). Honolulu Authority for Rapid Transit. Archived (PDF) from the original on February 15, 2017. Retrieved December 8, 2018.
- ^ Gutierrez, Ben (October 19, 2017). "In successful test, city rail cars reach 40 mph on its own power". Hawaii News Now. Retrieved November 15, 2024.
- ^ a b "Blaisdell hails Oahu mass transit project". Honolulu Star-Bulletin. May 24, 1966. pp. A12.
- ^ a b Reyes, B.J. (August 11, 2005). "Council gives transit go-ahead 13 years after initial rejection". Honolulu Star-Bulletin. Archived from the original on August 8, 2010. Retrieved October 16, 2008.
- ^ a b Carlson, Ragnar (September 3, 2008). "Hail to the chief". Honolulu Weekly. Archived from the original on September 28, 2011. Retrieved October 16, 2008.
- ^ a b Au, Laurie (October 19, 2008), "Voters can derail $4B project", Honolulu Star-Bulletin, archived from the original on June 1, 2010, retrieved March 8, 2011
- ^ a b Au, Laurie (November 10, 2008), "Voters on route drive rail victory", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved July 7, 2010
- ^ a b Park, Gene (February 12, 2011), "Rail ready to break ground", Honolulu Star-Advertiser, archived from the original on September 24, 2015, retrieved February 12, 2011
- ^ a b c Park, Gene (February 23, 2011), "It's a go!", Honolulu Star-Advertiser, vol. 130, no. 23, p. A1, archived from the original on September 24, 2015, retrieved February 23, 2011
- ^ "Fasi To Start Rail Transit Study", Honolulu Star-Bulletin & Advertiser, p. A1, February 16, 1969 (Note: At this time, the Honolulu Star-Bulletin and Honolulu Advertiser published Sunday editions jointly under the name Honolulu Star-Bulletin & Advertiser.)
- ^ Tune, Jerry (July 7, 1977), "A Transit Line with a HART", Honolulu Star-Bulletin, pp. A12
- ^ Matsunaga, Mark (February 19, 1981), "Reagan stops HART in its tracks", Honolulu Advertiser, p. A1
- ^ Matsunaga, Mark (May 5, 1981), "Mayor to abandon HART, beef up buses", Honolulu Advertiser, pp. A1
- ^ Glauberman, Stu (May 5, 1981), "Mayor Calls HART Study to Abrupt Halt", Honolulu Star-Bulletin, p. A1
- ^ Matsunaga, Mark (August 14, 1986), "Transit system plan revived", Honolulu Advertiser, p. A3
- ^ Mariani, Jeanne (September 23, 1992), "Rail line dead – for now", Honolulu Star-Bulletin, p. A1
- ^ Dicus, Howard (January 30, 2004), "Harris: 'Honolulu must build fixed rail'", Pacific Business News, archived from the original on July 6, 2008, retrieved October 16, 2008
- ^ Frosch, Dan; Overberg, Paul (March 22, 2019). "How a Train Through Paradise Turned Into a $9 Billion Debacle". Wall Street Journal.
- ^ Kua, Crystal (November 3, 2006), "Council panel backs rail as mass-transit solution", Honolulu Star-Bulletin, archived from the original on December 3, 2008, retrieved October 15, 2008
- ^ City and County of Honolulu Department of Transportation Services (November 1, 2006), Honolulu High-Capacity Transit Corridor Alternatives Analysis Report Chapter 1[permanent dead link ], Chapter 2[permanent dead link ], Chapter 3 to 7[permanent dead link ], retrieved February 25, 2009
- ^ U.S. Department of Transportation Federal Transit Administration; City and County of Honolulu Department of Transportation Services, Draft Environmental Impact Statement Executive Summary[permanent dead link ] (PDF), retrieved February 25, 2009
- ^ Au, Laurie (October 31, 2008), "City releases portion of rail report", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved July 7, 2010
- ^ Shikina, Robert (November 3, 2008), "Kobayashi rails against city for timing of report", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved November 6, 2008
- ^ Hao, Sean; Roig, Suzanne (November 3, 2008), "Hawaii rail transit cost now at least $4.34B", Honolulu Advertiser, archived from the original on July 12, 2011, retrieved March 5, 2011
- ^ U.S. Department of Transportation Federal Transit Administration; City and County of Honolulu Department of Transportation Services (2008-11), Honolulu High-Capacity Transit Corridor Project Draft Environmental Impact Statement/Section 4(f) Evaluation Cover to Contents[permanent dead link ], Chapter 1 Archived January 3, 2011, at the Wayback Machine, Chapter 2 Archived January 3, 2011, at the Wayback Machine, Chapter 3[permanent dead link ], Chapter 4 (Part 1) Archived January 3, 2011, at the Wayback Machine, Chapter 4 (Part 2)[permanent dead link ], Chapter 5[permanent dead link ], Chapters 6–8 Archived January 3, 2011, at the Wayback Machine, References to Index Archived April 14, 2010, at the Wayback Machine, Appendix A (Conceptual Alignment Plans and Profiles) Archived January 3, 2011, at the Wayback Machine, Appendix B (Conceptual Right-of-Way Plans)[permanent dead link ], Appendix C (Construction Approach) Archived December 11, 2009, at WebCite, Appendix D (Record of Agency Correspondence and Coordination)[permanent dead link ], Appendix E (Record of Public and Stakeholder Correspondence and Coordination) Archived January 3, 2011, at the Wayback Machine, retrieved on January 5, 2009
- ^ Hao, Sean (June 15, 2010), "Final study for rail line gets feds' OK", Honolulu Star-Advertiser, archived from the original on June 20, 2010, retrieved February 1, 2010
- ^ a b Park, Gene (January 19, 2011), "Rail gets OK to break ground", Honolulu Star-Advertiser, archived from the original on January 22, 2011, retrieved January 20, 2011
- ^ a b Hao, Sean (October 20, 2009), "Burial council won't sign rail pact", Honolulu Advertiser, archived from the original on June 10, 2011, retrieved July 7, 2010
- ^ Conrow, Joan (May 26, 2010), "grave matters", Honolulu Weekly, archived from the original on November 19, 2011, retrieved January 30, 2011
- ^ Park, Gene (January 16, 2011), "City plan accounts for problematic burial sites", Honolulu Star-Advertiser, archived from the original on January 19, 2011, retrieved January 30, 2011
- ^ Daranciang, Nelson (February 1, 2011), "Lawsuit claims rail endangers burial sites", Honolulu Star-Advertiser, vol. 129, no. 364, p. B1, archived from the original on February 13, 2011, retrieved February 1, 2011
- ^ Daranciang, Nelson (March 24, 2011), "Judge Rejects Suit Challenging Rail Survey", Honolulu Star-Advertiser, archived from the original on September 18, 2012, retrieved March 24, 2011
- ^ Hervey, Tiffany (June 27, 2012), "Buried Truth", Honolulu Weekly, archived from the original on October 25, 2012, retrieved July 19, 2012
- ^ Grube, Nick (August 24, 2012), "Rail Derailed? Hawaii Supreme Court Rules Against Honolulu", Honolulu Civil Beat, Peer News LLC, archived from the original on November 5, 2013, retrieved August 24, 2012
- ^ Schwind, Paul (January 3, 2013). "Honolulu Rail Remedy – Phasers On Minimal". Web. Hawaii Reporter. Archived from the original on November 5, 2013. Retrieved January 17, 2013.
- ^ Au, Laurie (September 10, 2008), "Mayoral debate turns raucous", Honolulu Star-Bulletin, archived from the original on January 24, 2009, retrieved October 16, 2008
- ^ Borreca, Richard; Au, Laurie (September 21, 2008), "Hannemann and Kobayashi reset sights for Nov. 4", Honolulu Star-Bulletin, archived from the original on September 25, 2008, retrieved October 20, 2008
- ^ Au, Laurie (November 5, 2008), "Hannemann win re-election with 58%", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved November 5, 2008
- ^ Au, Laurie (April 22, 2008), "Rail critics utilize power of pen", Honolulu Star-Bulletin, archived from the original on August 7, 2010, retrieved October 20, 2008
- ^ Au, Laurie (August 5, 2008), "Lawsuit looms over validity of anti-rail petition", Honolulu Star-Bulletin, archived from the original on February 21, 2009, retrieved November 6, 2008
- ^ Section 3-404 Archived September 18, 2008, at the Wayback Machine (PDF), Revised Charter of Honolulu Archived September 7, 2008, at the Wayback Machine, retrieved on February 25, 2009
- ^ Au, Laurie (August 20, 2008), "City clerk rushing to certify anti-rail effort", Honolulu Star-Bulletin, archived from the original on December 9, 2009, retrieved November 6, 2008
- ^ Au, Laurie (September 4, 2008), "Anti-rail group's effort denied by courts, clerk", Honolulu Star-Bulletin, archived from the original on September 27, 2008, retrieved November 6, 2008
- ^ Au, Laurie (August 21, 2008), "Council OKs ballot question on transit", Honolulu Star-Bulletin, archived from the original on September 24, 2009, retrieved November 12, 2008
- ^ Au, Laurie (August 22, 2008), "Mayor vows to put transit on ballot", Honolulu Star-Bulletin, archived from the original on September 4, 2009, retrieved November 12, 2008
- ^ Dayton, Kevin (January 11, 2019). "Premature contracts increased rail cost by $354M". Star-Advertiser. Honolulu. Archived from the original on March 17, 2020. Retrieved January 11, 2019.
- ^ Charles Djou, "Rail" (http://djou.com/issues/rail/ Archived October 30, 2016, at the Wayback Machine)
- ^ Mendoza, Jim; Lincoln, Mileka; Davis, Chelsea (June 16, 2016). "Mayor wants to shorten rail route, ending at Middle Street". Hawaii News Now. Archived from the original on April 3, 2017. Retrieved March 11, 2017.
- ^ Lee, Grace (May 18, 2016). "Mayoral candidate Peter Carlisle says rail project cannot be stopped". Hawaii News Now. Archived from the original on July 9, 2023. Retrieved June 15, 2024.
- ^ Hao, Sean (January 3, 2010), "Honolulu rail behind schedule, with construction start unclear", Honolulu Advertiser, archived from the original on December 14, 2010, retrieved February 1, 2011
- ^ Hao, Sean; Pang, Gordon Y.K. (January 9, 2010), "Honolulu's rail costs put state at financial risk, governor says", Honolulu Advertiser, archived from the original on December 14, 2010, retrieved February 1, 2011
- ^ Hao, Sean (August 26, 2010), "Time short for Lingle's call on rail", Honolulu Star-Advertiser, archived from the original on August 29, 2010, retrieved February 1, 2011
- ^ a b "Carlisle dismisses Lingle's rail report". Pacific Business News. December 3, 2010. Archived from the original on August 6, 2017. Retrieved September 1, 2017.
- ^ DePledge, Derrick (November 5, 2010), "Abercrombie to weigh rail EIS", Honolulu Star-Advertiser, archived from the original on September 13, 2012, retrieved February 1, 2011
- ^ Park, Gene (December 17, 2010), "Governor signs off on review of rail", Honolulu Star-Advertiser, archived from the original on January 20, 2011, retrieved February 1, 2011
- ^ Park, Gene (January 13, 2011), "State skips hearing on rail finance studies", Honolulu Star-Advertiser, archived from the original on September 13, 2012, retrieved February 1, 2011
- ^ Park, Gene (February 20, 2011), "If they build it, will developers come?", Honolulu Star-Advertiser, archived from the original on February 22, 2011, retrieved February 20, 2011
- ^ LaFrance, Adrienne (February 21, 2011), "Rail Groundbreaking: Phony or For Real?", Honolulu Civil Beat, Peer News LLC, archived from the original on March 1, 2011, retrieved February 22, 2011
- ^ "Chapter 22 Honolulu Authority for Rapid Transportation" (PDF). City and County of Honolulu. 2013.
- ^ "About". Honolulu Authority for Rapid Transportation. Archived from the original on June 1, 2023. Retrieved June 19, 2023.
- ^ a b "Danial Grabauskas Named HART Executive Director". City and County of Honolulu: Department of Customer Services. March 1, 2012. Archived from the original on May 11, 2018. Retrieved January 11, 2019.
- ^ "Honolulu rail CEO blames cost overruns on legal challenges, but critics say it is incompetence". August 15, 2014. Archived from the original on September 6, 2017. Retrieved September 6, 2017.
- ^ "Editorial: COVID-19 brings more delays and money problems for Honolulu's rail". Honolulu Star Advertiser. May 16, 2020. Archived from the original on May 23, 2020. Retrieved May 25, 2020.
- ^ Honore, Marcel (May 12, 2020). "City Council Grows Anxious As Rail's COVID-19 Problems Deepen". Honolulu Civil Beat. Archived from the original on May 23, 2020. Retrieved May 25, 2020.
- ^ Honore, Marcel (November 24, 2020). "Rail's Interim Service Could Be Pushed Back A Year Amid COVID-19, Testing Woes". Honolulu Civil Beat. Archived from the original on January 5, 2021. Retrieved January 2, 2021.
- ^ "HART, Hitachi At Odds Over Wheel Defect As Rail Costs Soar". Honolulu Civil Beat. March 19, 2021. Archived from the original on May 14, 2021. Retrieved May 14, 2021.
- ^ "Wheels don't fit tracks on Honolulu's beleaguered rail line". AP NEWS. May 7, 2021. Archived from the original on May 14, 2021. Retrieved May 14, 2021.
- ^ Fuji-Oride, Noelle (November 9, 2021). "How Rail Got to $12.45 Billion and 11 Years Late". Hawaii Business. Archived from the original on January 27, 2022. Retrieved November 18, 2021.
- ^ "Honolulu rail CEO offers new hope to repair gap between rail wheels and track". Honolulu Star Advertiser. December 8, 2021. Archived from the original on January 28, 2022. Retrieved January 28, 2022.
- ^ Honore, Marcel (November 9, 2021). "HART Has A Plan To Fix Rail Tracks But Lacks Welders To Do The Work". Honolulu Civil Beat. Archived from the original on January 28, 2022. Retrieved January 28, 2022.
- ^ a b "Honolulu ranked worst in country for traffic". Hawaii News Now. May 23, 2012. Archived from the original on September 14, 2017. Retrieved August 31, 2017.
- ^ "Honolulu Rail Final EIS, Table 3-12" (PDF). hartdocs.honolulu.gov. Archived (PDF) from the original on January 26, 2022. Retrieved November 4, 2020.
- ^ Weingart, Eden; Schukar, Alyssa (January 6, 2023). "Widening Highways Doesn't Fix Traffic. So Why Do We Keep Doing It?". The New York Times. ISSN 0362-4331. Archived from the original on June 23, 2023. Retrieved July 2, 2023.
- ^ "What Can We Do About the Rail? Nothing. Tackle Traffic Congestion!". Honolulu City Beat. January 29, 2015. Archived from the original on August 31, 2017. Retrieved August 31, 2017.
- ^ Kojima, Craig T. (2016). "Feds to city: No more money for rail, no stopping at Middle Street". Honolulu Star Advertiser. Archived from the original on September 1, 2016. Retrieved August 31, 2016.
- ^ Nanea Kalani (September 1, 2017). "Rail bail-out bill goes to Ige after House approves". Honolulu Star Advertiser. Archived from the original on September 2, 2017. Retrieved September 2, 2017.
- ^ "Rail officials start over on selecting builder for last stretch". Honolulu Star Advertiser. September 8, 2017. Archived from the original on November 25, 2020. Retrieved September 25, 2017.
- ^ a b "HART awards $400 million contract to relocate utilities to make way for Honolulu rail". Honolulu Star-Advertiser. May 7, 2018. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ a b "Rail transit system cost estimate: $3 billion". Honolulu Advertiser. June 23, 2006. Archived from the original on September 1, 2017. Retrieved September 1, 2017.
- ^ "For Cost Overruns, Honolulu Rail Is In A League Of Its Own, New Data Shows". Honolulu Civil Beat. August 9, 2021. Archived from the original on September 11, 2021. Retrieved September 11, 2021.
- ^ "The Hard Reality Of Honolulu Rail Costs". Honolulu Civil Beat. August 25, 2017. Archived from the original on September 6, 2017. Retrieved September 6, 2017.
- ^ "City rail audit won't look for fraud?". Grassroot Institute. August 18, 2017. Archived from the original on September 20, 2017. Retrieved September 20, 2017.
- ^ "Rep Tupola Backs Forensic Audit for HART". Hawai`i Free Press. August 15, 2017. Archived from the original on September 20, 2017. Retrieved September 20, 2017.
- ^ a b c "Honolulu rail bailout becomes law with Ige's signature". Honolulu Star Advertiser. September 5, 2017. Archived from the original on September 6, 2017. Retrieved September 6, 2017.
- ^ a b "Bring Honolulu Rail Down To Earth". Honolulu Civic Beat. September 27, 2017. Archived from the original on September 29, 2017. Retrieved September 28, 2017.
- ^ Nakaso, Dan (March 11, 2021). "Honolulu Rail Project: $3B Deficit and No Recovery Plan". Governing.
- ^ Kua, Crystal (January 1, 2005), "Director prioritizes rail transit", Honolulu Star-Bulletin, archived from the original on August 8, 2010, retrieved October 16, 2008
- ^ Kua, Crystal (May 5, 2005), "City measure touts rail tax", Honolulu Star-Bulletin, archived from the original on August 8, 2010, retrieved October 16, 2008
- ^ a b c d State of Hawaii Department of Taxation (July 29, 2005), State of Hawaii Department of Taxation Announcement 2005-11 (PDF), archived from the original (PDF) on December 21, 2009, retrieved June 21, 2009
- ^ a b Kua, Crystal (July 12, 2005), "Late deal avoids transit veto", Honolulu Star-Bulletin, archived from the original on August 8, 2010, retrieved October 16, 2008
- ^ a b Zimmerman, Malia (July 12, 2005), "Surrounded By Democrats at the Capitol, Hawaii's Republican Governor Rescinds Decision to Veto Tax Increase Measure", Hawaii Reporter, archived from the original on August 9, 2007, retrieved October 16, 2008
- ^ DePledge, Derrick; Dingeman, Robbie (July 12, 2005), "Deal puts transit tax back on track", Honolulu Advertiser, p. A1, archived from the original on June 10, 2011, retrieved July 7, 2010
- ^ Kua, Crystal (August 11, 2005), "Transit project to raise taxes", Honolulu Star-Bulletin, archived from the original on August 8, 2010, retrieved October 16, 2008
- ^ Kua, Crystal (August 24, 2005), "Mayor signs tax, calls for multi-faceted traffic solutions", Honolulu Star-Bulletin, archived from the original on August 8, 2010, retrieved October 16, 2008
- ^ Daranciang, Nelson (December 31, 2006), "Excise tax increase begins tomorrow", Honolulu Star-Bulletin, archived from the original on August 8, 2010, retrieved February 2, 2011
- ^ Wu, Nina (January 22, 2009), "Legislature battles to avert $1.8B deficit", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved July 7, 2010
- ^ DePledge, Derrick; Boylan, Peter (June 21, 2009), "Governor emphasizes Hawaii's deficit woes as Legislature opens", Honolulu Advertiser, archived from the original on December 15, 2010, retrieved June 21, 2009
- ^ Hawaii State Legislature, 2009 Regular Session, Senate Bill 1626 Status, archived from the original on June 15, 2009, retrieved June 21, 2009
- ^ Hawaii State Legislature, Senate Bill 1626 Senate Draft 1, Relating to Taxation, archived from the original on June 10, 2011, retrieved June 21, 2009
- ^ Nakaso, Dan (January 24, 2009), "Stimulus could revive Honolulu, mayor says", Honolulu Advertiser, archived from the original on December 15, 2010, retrieved June 21, 2009
- ^ DePledge, Derrick (March 11, 2009), "Legislature keeping its tax-raising options open", Honolulu Advertiser, archived from the original on December 15, 2010, retrieved June 21, 2009
- ^ Borreca, Richard (March 11, 2009), "Lawmakers fear revenue slump", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved July 7, 2010
- ^ "City Council approves tax surcharge extension for Honolulu rail project". Hawaii News Now. January 28, 2016. Archived from the original on September 2, 2017. Retrieved September 2, 2017.
- ^ a b "$2.4 Billion Rescue Bill For Honolulu Rail Wins Final Approval". Honolulu City Beat. September 2, 2017. Archived from the original on September 2, 2017. Retrieved September 2, 2017.
- ^ a b "New 'worst-case scenario' report reveals full 20-mile rail route could cost $10.79B". Hawaii News Now. June 24, 2016. Archived from the original on September 6, 2017. Retrieved September 6, 2017.
- ^ Ray Tsuchiyama (June 29, 2016). "A Rail System Option That Offers The Best Fit For Honolulu". Honolulu Civil Beat. Archived from the original on June 30, 2016. Retrieved June 29, 2016.
- ^ "Salvage the Rail: Group renews call to bring rail to street level". Island News KITV4. February 7, 2017. Archived from the original on September 28, 2017. Retrieved September 28, 2017.
- ^ "MODIFYING HONOULU AREA RAPID TRANSIT (HART) FOR STREET LEVEL OPERATION IN DOWNTOWN HONOLULU (January 2017)" (PDF). Salvage The Rail. Archived (PDF) from the original on September 28, 2017. Retrieved September 28, 2017.
- ^ a b "HART committed to rail project's original route in recovery plan submitted to FTA". Pacific Business News. May 1, 2017. Archived from the original on August 15, 2017. Retrieved August 15, 2017.
- ^ a b c "HART Recovery Plan". Honolulu Authority for Rapid Transportation. April 28, 2017. Archived from the original (PDF) on August 31, 2017. Retrieved August 15, 2017.
- ^ a b "The Estimated Cost Of Honolulu Rail Just Dropped By $1 Billion". September 18, 2017. Archived from the original on September 25, 2017. Retrieved September 25, 2017.
- ^ "Honolulu Rail Recovery Plan Remains A Work In Progress". Honolulu Civil Beat. January 8, 2018. Archived from the original on January 11, 2018. Retrieved January 11, 2018.
- ^ "Feds serve Honolulu's rail agency with 2nd subpoena". Archived from the original on April 29, 2022. Retrieved July 3, 2019.
- ^ "Honolulu rail project subpoenaed by feds for third time". Archived from the original on April 29, 2022. Retrieved July 3, 2019.
- ^ Dayton, Kevin (September 5, 2019). "FTA approves Honolulu rail recovery plan". Honolulu Star-Advertiser. Archived from the original on December 11, 2019. Retrieved December 27, 2019.
- ^ Honore, Marcel (November 19, 2020). "City Pushes Rail's Opening To 2033, Price Tag Soars To $11 Billion". Honolulu Civil Beat. Retrieved July 2, 2023.
- ^ Honore, Marcel (March 12, 2021). "Honolulu Rail Has A New Price Tag: $12.4 Billion". Honolulu Civil Beat. Retrieved July 2, 2023.
- ^ a b c d Wanek-Libman, Mischa (July 3, 2023). "Honolulu's Skyline opens for service". Mass Transit. Retrieved July 6, 2023.
- ^ Aquino, Jamm; Russell, Cindy Ellen (June 30, 2023). "Ridership commences on Honolulu's rail system". Honolulu Star-Advertiser. Retrieved July 2, 2023.
- ^ Sneider, Julie (August 2019). "Honolulu transit leaders eye late 2020 start to city's first passenger-rail system". Progressive Railroading. Archived from the original on April 4, 2020. Retrieved December 17, 2019.
- ^ a b "Honolulu Rail Transit Project Overview" (PDF). Honolulu Authority for Rapid Transportation. October 2016. Archived (PDF) from the original on October 23, 2020. Retrieved December 19, 2019.
- ^ a b c "Construction". Honolulu Authority for Rapid Transportation. Archived from the original on June 15, 2024. Retrieved June 15, 2024.
- ^ a b Honolulu Authority for Rapid Transit. "Rail Facts". Archived from the original on November 1, 2016. Retrieved November 26, 2016.
- ^ a b c d "HART: Expect Honolulu's Full Rail Line To Be Done In 2031". Honolulu Civil Beat. March 10, 2021. Archived from the original on April 2, 2021. Retrieved September 20, 2021.
- ^ a b "'A 21st century system': To fanfare, city announces official opening date of rail's first phase". Hawaii News Now. May 9, 2023. Retrieved May 10, 2023.
- ^ a b Broder van Dyke, Michelle (June 14, 2024). "Second segment of Skyline will be energized". Spectrum Local News. Archived from the original on June 15, 2024. Retrieved June 15, 2024.
- ^ a b "FAQs". Honolulu Authority for Rapid Transportation. Retrieved June 21, 2023.
- ^
- "West Oahu-Farrington Highway Guideway Contract for Design-Build Construction Contract No. SC-DTS-1000137". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "West Oahu Station Group -FD Contract No. SC-HRT-1200116". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "West Oahu Stations Group Construction Contract". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Farrington Hwy Station Group Design Contract No. SC-HRT-11H0013". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Farrington Highway Station Group Construction Contract". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Farrington Highway Station Group II". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Kamehemeha [sic] Highway Guideway Design Build Contract No. CT-HRT-11H00195". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Kamehameha Highway Station Group Design Consultant Contract No. CT-HRT-130022". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Kamehameha Highway Stations Group Construction Contract No. CT-HRT-1600152". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^
- "Airport Segment Guideway and Utilities Contract No. SC-HRT-1200038". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Airport Station Group Design Consultant Contract No. SC-HRT-1200038". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- "Airport Guideway and Stations Design-Build Contract No. CT-HRT-1600385". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- GALM, Internal Audit, and Project Oversight Committee Meeting (April 13, 2023). YouTube. Retrieved April 18, 2023.
- ^ "City Center Section Utilities & Guideway Contract No. SC-HRT-1200149". Honolulu Authority for Rapid Transportation. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ a b "Shortened Honolulu rail plan approved by Federal Transit Administration". Hawai'i Public Radio. September 30, 2022. Retrieved April 28, 2023.
- ^ a b "First contract awarded for Honolulu light rail". Railway Gazette International. October 26, 2009. Archived from the original on October 31, 2009. Retrieved October 26, 2009.
- ^ Hao, Sean (October 22, 2009), "1st Honolulu Rail Contract Goes to Kiewit Pacific at $483M", Honolulu Advertiser, archived from the original on June 10, 2011, retrieved July 7, 2010
- ^ Tim Sakahara, "Concrete poured on Honolulu rail project Archived September 27, 2020, at the Wayback Machine," Hawaii News Now, May 16, 2014, retrieved on October 29, 2014.
- ^ Hao, Sean (February 25, 2008). "First phase of rail would end in Pearl City". Honolulu Advertiser. Archived from the original on July 6, 2008. Retrieved March 16, 2009.
- ^ a b c d Rodriguez, Jose (Summer 2015). "Honolulu Rail Transit Project (Segments 1 and 2)" (PDF). ASPIRE: The Concrete Bridge Magazine. Precast/Prestressed Concrete Institute. Archived (PDF) from the original on October 7, 2020. Retrieved December 19, 2019.
- ^ Cox, William R. (Summer 2013). "Rail Transit Bridges" (PDF). ASPIRE: The Concrete Bridge Magazine. Precast/Prestressed Concrete Institute. Archived (PDF) from the original on March 17, 2020. Retrieved December 19, 2019.
- ^ "The Honolulu Rail Transit Project Honolulu, Hawaii – Construction Update". Segments. Vol. 59. American Segmental Bridge Institute. Fall 2014. Archived from the original on August 1, 2020. Retrieved December 19, 2019.
- ^ Daysog, Rick (April 18, 2014). "Rail system's new concrete casting yard". Archived from the original on December 19, 2019. Retrieved December 19, 2019.
- ^ a b Honolulu Rail Transit Project Update (PDF) (Report). Honolulu Chamber of Commerce. June 25, 2014. Archived (PDF) from the original on December 19, 2019. Retrieved December 19, 2019.
- ^ "Honolulu Rail Transit". Somerset Engineering. Archived from the original on December 19, 2019. Retrieved December 19, 2019.
- ^ Time Lapse – Balanced Cantelevered Work over H1/H2 Merge on YouTube
- ^ "Rail project's balanced cantilever work over H-1 in Pearl City finishing up". KHON2. September 17, 2016. Archived from the original on December 19, 2019. Retrieved December 19, 2019.
- ^ "AECOM announced today that it had been awarded a US$38.8-million contract to design the airport segment of the Honolulu Rail transit Project in Hawaii" (Press release). AECOM Technology Corporation. January 27, 2012. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ Tobias, Lori (August 31, 2016). "Hawaii's $8B HART Project Is Chugging Along". Construction Equipment Guide. Archived from the original on December 19, 2019. Retrieved December 19, 2019.
- ^ Lincoln, Mileka (July 19, 2016). "Successful Airport-Middle Street rail segment bid totals $875M". Hawaii News Now. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ Parsons, Jim (September 13, 2017). "Funding Boost Shores Up Troubled Honolulu Rail Project". Engineering News-Record. Archived from the original on December 19, 2019. Retrieved December 19, 2019.
- ^ Consillio, Kristen (November 17, 2008), "Rail route changes trigger harsh words", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved July 7, 2010
- ^ Kua, Crystal (February 22, 2007), "Rail Route to Go Via Salt Lake", Honolulu Star-Bulletin, archived from the original on May 4, 2010, retrieved January 18, 2008
- ^ Au, Laurie (January 29, 2008), "New rail route OK'd", Honolulu Star-Bulletin, archived from the original on October 21, 2012, retrieved July 7, 2010
- ^ a b Hao, Sean (January 29, 2009), "Council changes transit route to serve airport", Honolulu Advertiser, archived from the original on December 15, 2010, retrieved January 29, 2002
- ^ "Honolulu Authority for Rapid Transportation (HART) Airport Guideway & Stations". Finley Engineering Group. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "Honolulu Rail Transit Project (HART)". McNary Bergeron & Associates. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "Airport Guideway and Stations Design-Build Contrat". Traylor Bros., Inc. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "HART contractor drills largest, deepest column foundation to support the Honolulu Rail project" (PDF) (Press release). Honolulu Authority for Rapid Transportation. June 15, 2020. Archived (PDF) from the original on January 9, 2021. Retrieved January 7, 2021.
- ^ "HART Airport Guideway and Stations Project – Honolulu, Hawaii". RJ Watson Inc. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "HART rail contractor reaches major milestone with completion of final precast segment" (PDF) (Press release). Honolulu Authority for Rapid Transportation. December 10, 2020. Archived (PDF) from the original on August 13, 2021. Retrieved December 30, 2020.
- ^ "Parsons (PSN) Secures Role in the $1.66B Honolulu Rail Project". MSN. August 15, 2024. Retrieved August 26, 2024.
- ^ "HART announces $1.6B contract award for construction of next rail segment". Hawaii News Now. August 15, 2024. Retrieved August 26, 2024.
- ^ Yoshioka, Wayne (May 14, 2018). "HART Looking For Private Partners to Complete Last $1.6B City Center Rail Segment". Hawaiʻi Public Radio. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "Public-Private Partnership Development Program | Program Structure". Executive Matters and Legal Affairs Committee, City and County of Honolulu. April 16, 2019. Archived from the original on October 5, 2020. Retrieved December 20, 2019.
- ^ "HART & city issue initial P3 request for proposals" (Press release). Honolulu Authority for Rapid Transportation. Archived from the original on October 22, 2020. Retrieved December 30, 2020.
- ^ "HART and city receive P-3 proposals" (PDF) (Press release). Honolulu Authority for Rapid Transportation. July 23, 2020. Archived (PDF) from the original on October 19, 2020. Retrieved December 30, 2020.
- ^ a b Honore, Marcel (December 15, 2020). "HART, City Underestimated Cost Of Rail Work By $1.3 Billion, P3 Prices Show". Honolulu Civil Beat. Archived from the original on December 30, 2020. Retrieved December 30, 2020.
- ^ Honore, Marcel (November 20, 2020). "'How Do We Go Forward?' Honolulu Rail Leaders Kill P3, Confront Unknown Costs". Honolulu Civil Beat. Archived from the original on December 30, 2020. Retrieved December 30, 2020.
- ^ "HART issues request for information for work to complete rail project construction" (PDF) (Press release). Honolulu Authority for Rapid Transportation. December 14, 2020. Archived (PDF) from the original on August 14, 2021. Retrieved December 30, 2020.
- ^ Dayton, Kevin (June 26, 2023). "Honolulu Rail Spent $100 Million To Relocate Utilities. Much Of It May Have Been A Waste". Honolulu Civil Beat. Archived from the original on March 3, 2024. Retrieved June 15, 2024.
- ^ Gutierrez, Ben (October 13, 2022). "Prep work for rail accelerates along Nimitz Highway". Hawaii News Now. Archived from the original on March 3, 2024. Retrieved June 15, 2024.
- ^ Tsai, Michael (October 12, 2022). "Work to start on rail's $496M 'mauka shift' along Dillingham". Spectrum Local News. Archived from the original on March 2, 2024. Retrieved June 15, 2024.
- ^ Dayton, Kevin (October 12, 2023). "Rail Changes Planned For Kakaako Mean Fewer Trees, More Buses". Honolulu Civil Beat. Archived from the original on March 3, 2024. Retrieved June 15, 2024.
- ^ https://www.civilbeat.org/2024/08/hart-reaches-huge-milestone-with-contract-award-for-city-center-guideway-and-6-stations/
- ^ City and County of Honolulu Department of Transportation Services, Rail Transit Map (Part 1: Kapolei-Ewa)[permanent dead link ], (Part 2: Waipahu-Aiea)[permanent dead link ], (Part 3: Stadium-Kalihi)[permanent dead link ], (Part 4: Kalihi-UH-Manoa/Waikiki)[permanent dead link ], retrieved January 5, 2009
- ^ "2: Alternatives Considered" (PDF). Honolulu High-Capacity Transit Corridor Project: Final Environmental Impact Statement/Section 4(f) Evaluation (Report). Department of Transportation Services, City and county of Honolulu. June 2010. pp. 2–48. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ Kalani, Nanea (November 18, 2017). "Rail authority looks to preserve corridor for University of Hawaiʻi at Mānoa option". Honolulu Star Advertiser. Archived from the original on December 13, 2017. Retrieved December 12, 2017.
- ^ "Complete Streets - Waikiki". February 6, 2024.
- ^ "University, McCully, & Metcalf Complete Streets". February 25, 2024.
- ^ "Kapolei Maintenance Facility and Transit Center" (PDF). City and County of Honolulu. Archived (PDF) from the original on February 24, 2024. Retrieved June 15, 2024.
- ^ "Kaoplei Lots". City and County of Honolulu. Archived from the original on December 11, 2021. Retrieved June 15, 2024.
- ^ "Phase 3 Presentation from April 29, 2021". April 6, 2022.
- ^ "HART awards construction contract for West Oahu rail stations" (PDF) (Press release). Honolulu Authority for Rapid Transportation. July 16, 2015. Archived (PDF) from the original on August 1, 2020. Retrieved December 20, 2019.
- ^ Honoré, Marcel (December 23, 2015). "NAN Inc. wins deal for last trio of transit stations". Honolulu Star-Advertiser. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "Farrington Highway Stations Group Construction Contract No. CT-HRT-1500236" (PDF). June 10, 2015. Archived (PDF) from the original on February 17, 2017. Retrieved December 20, 2019.
- ^ Mendoza, Jim (October 26, 2017). "It's coming: Rail work kicks off airport leg". Hawaii News Now. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "Hawaiian Names for Rail Stations". Honolulu Authority for Rapid Transportation. Archived from the original on September 21, 2021. Retrieved July 2, 2023.
- ^ "Hawaiian Station Naming Program" (PDF). Honolulu Authority for Rapid Transportation. November 22, 2017. Archived (PDF) from the original on August 1, 2020. Retrieved December 19, 2019.
- ^ "HART Board of Directors unanimously approve Hawaiian names for first nine rail stations" (PDF) (Press release). Honolulu Authority for Rapid Transportation. February 22, 2018. Archived (PDF) from the original on August 1, 2020. Retrieved December 19, 2019.
- ^ Wu, Nina (April 18, 2019). "Honolulu rail transit authority seeks feedback on Hawaiian names for train stations". Honolulu Star-Advertiser. Archived from the original on May 30, 2019. Retrieved May 29, 2019.
- ^ "Hawaiian names recommended for HART's rail stations" (PDF) (Press release). Honolulu Authority for Rapid Transportation. April 17, 2019. Archived (PDF) from the original on March 17, 2020. Retrieved December 19, 2019.
- ^ Boneza, Jenn (June 16, 2023). "City cites safety, vandalism as reasons for excluding open public restrooms from Skyline". KHON2. Archived from the original on July 11, 2023. Retrieved July 10, 2023.
- ^ "Route Map". Honolulu Authority for Rapid Transportation. Archived from the original on June 27, 2023. Retrieved June 27, 2023.
- ^ "Skyline Stations". City and County of Honolulu. June 23, 2023. Archived from the original on June 24, 2023. Retrieved June 27, 2023.
- ^ "Ahupaa Map" (PDF). Honolulu Authority for Rapid Transportation. May 25, 2012. Archived (PDF) from the original on August 1, 2020. Retrieved December 18, 2019.
- ^ City and County of Honolulu Department of Transportation Services. "Q&A: Honolulu Rail Transit" (PDF). Archived from the original (PDF) on January 17, 2009. Retrieved January 5, 2009.
- ^ Nakas (July 2, 2023). "Rail ridership projections, revenue uncertain after Skyline opens". Honolulu Star-Advertiser. p. A10. Retrieved July 5, 2023.
- ^ "City to announce grand opening date for first phase of long-delayed rail project". Hawaii News Now. Facebook. May 10, 2023. Retrieved June 10, 2023.
- ^ Bussewitz, Cathy (August 26, 2017). "Hawaii scrambles to keep train project from going off rails". AP News. Archived from the original on December 20, 2019. Retrieved December 20, 2019.
- ^ "City announces initial Skyline ridership during free-fare period". City and County of Honolulu. July 5, 2023. Archived from the original on July 7, 2023. Retrieved July 6, 2023.
- ^ Mattos, Shelby (July 5, 2023). "Nearly 72,000 passengers rode Skyline during its opening weekend". KITV Island News. Archived from the original on July 6, 2023. Retrieved July 6, 2023.
- ^ "Transit Ridership Report Fourth Quarter 2023" (PDF). American Public Transportation Association. March 4, 2024. Retrieved September 5, 2024.
- ^ "Transit Ridership Report Second Quarter 2024" (PDF). American Public Transportation Association. September 3, 2024. Retrieved September 5, 2024.
- ^ "Skyline Ridership Summary September 2024" (PDF). Honolulu Department of Transportation Services. October 31, 2024. Retrieved October 31, 2024.
- ^ "Skyline - Ridership". Honolulu Department of Transportation Services. Retrieved October 31, 2024.
- ^ "Skyline Rail Operations". City and County of Honolulu. June 19, 2023. Retrieved June 25, 2023.
- ^ "Fares & Passes". TheBus. Retrieved June 25, 2023.
- ^ "Riding Skyline Episode 2: Go Holo with your HOLO card". Honolulu Department of Transportation Services. YouTube. June 29, 2023.
- ^ "Honolulu Rail Transit Project: System Resource Guide" (PDF). Honolulu Authority for Rapid Transportation. Archived (PDF) from the original on August 2, 2020. Retrieved December 19, 2019.
- ^ "Agreement for Design-Build Services, Contract No. CT-DTS-1000449" (PDF). Honolulu High-Capacity Transit Corridor Project. June 30, 2011. Archived (PDF) from the original on August 1, 2020. Retrieved December 23, 2019.
- ^ Honolulu Rail Transit Project Monthly Progress Report (PDF) (Report). Honolulu Authority for Rapid Transportation. July 2016. Archived (PDF) from the original on August 1, 2020. Retrieved December 23, 2019.
- ^ "Hannemann: If It's Not Steel on Steel, I'll Pull the Plug". www.hawaiinewsnow.com. April 18, 2008. Archived from the original on April 29, 2022. Retrieved April 22, 2022.
- ^ a b Vantuono, William C. (June 30, 2023). "'Skyline' Opens in Honolulu". Railway Age. Retrieved July 2, 2023.
- ^ "RAIL SAFETY DATA REPORT" (PDF). Federal Transit Administration. September 1, 2021. Retrieved July 17, 2024.
- ^ "Home". honolulutransit.org. Archived from the original on July 28, 2014. Retrieved September 30, 2014.
- ^ "Train Vehicle Fact Sheet" (PDF). Archived (PDF) from the original on July 31, 2022.
- ^ Park, Gene (March 22, 2011), "Have a seat", Honolulu Star-Advertiser, vol. 130, no. 50, p. A1, A6, archived from the original on August 8, 2014, retrieved March 22, 2011
- ^ U.S. Department of Transportation Federal Transit Administration; City and County of Honolulu Department of Transportation Services (June 2010), Honolulu High-Capacity Transit Corridor Project Final Environmental Impact Statement/Section 4(f) Evaluation (PDF), pp. 2–30, archived (PDF) from the original on September 2, 2017, retrieved March 28, 2011
- ^ a b "Agreement for Design-Build-Operate-Maintain Services, Contract No. CT-DTS-1100194" (PDF). Honolulu High-Capacity Transit Corridor Project. November 28, 2011. Archived (PDF) from the original on February 10, 2017. Retrieved December 23, 2019.
- ^ Brown, Robert (April 15, 2011), "Fact Check — Carlisle: Ansaldo's Copenhagen Line One of World's Best", Honolulu Civil Beat, Peer News LLC, archived from the original on July 22, 2011, retrieved April 16, 2011
- ^ "Hitachi agrees to buy Ansaldo STS and AnsaldoBreda". Railway Gazette. February 24, 2015. Archived from the original on November 1, 2020. Retrieved February 25, 2015.
- ^ Park, Gene (April 12, 2011), "2 bidders protest city's rail decision", Honolulu Star-Advertiser, vol. 130, no. 71, archived from the original on September 19, 2012, retrieved April 12, 2011
- ^ Kalani, Nanea (October 14, 2011). "Disqualified Honolulu Rail Bidder Bombardier Files New Appeal". Honolulu Civil Beat. Peer News. Archived from the original on August 7, 2013. Retrieved July 13, 2013.
- ^ Abramson, Mark (October 17, 2012). "Hawaii Appeals Court upholds ruling in Bombardier rail lawsuit". Pacific Business News. American City Business Journals. Archived from the original on October 19, 2012. Retrieved July 13, 2013.
- ^ Bombardier Transportation (Holdings) USA Inc. v. Director, Department of Budget and Fiscal Services, City and County of Honolulu Archived October 24, 2012, at the Wayback Machine, 128 Haw. 413 (App.), 289 P.3d 1049 (Haw. App. 2012)
- ^ a b Barrow, Keith (March 29, 2016). "First Honolulu metro cars delivered". International Railway Journal. Archived from the original on December 23, 2019. Retrieved December 23, 2019.
- ^ Honoré, Marcel (March 24, 2016). "First train cars arrive in Honolulu for rail transit project". Honolulu Star-Advertiser. Archived from the original on December 23, 2019. Retrieved December 23, 2019.
- ^ "Honolulu Gets First Look at New Transit System Rail Cars" (Press release). Hitachi USA. May 2, 2016. Archived from the original on December 23, 2019. Retrieved December 23, 2019.
- ^ Honoré, Marcel (December 16, 2016). "New defect could further stall rail". Honolulu Star-Advertiser. Archived from the original on September 8, 2017. Retrieved September 8, 2017.
- ^ "Repairs to fix rail-car production defects scheduled to start in March". KHON2. February 18, 2017. Archived from the original on September 8, 2017. Retrieved September 8, 2017.
- ^ "Honolulu tests rail car on track for first time". Honolulu Star-Advertiser. May 30, 2017. Archived from the original on September 8, 2017. Retrieved September 8, 2017.
- ^ "In successful test, city rail cars reach 40 mph on its own power". Hawaii News Now. October 19, 2017. Archived from the original on October 20, 2017. Retrieved October 20, 2017.
- ^ "StarBulletin.com | News | /2006/02/19/". archives.starbulletin.com. Archived from the original on October 4, 2020. Retrieved September 10, 2020.
- ^ "Just the facts on Honolulu transit". October 12, 2008. Archived from the original on September 1, 2017. Retrieved September 1, 2017.
- ^ "Council OKs ballot question on transit". Honolulu Star Bulletin. Archived from the original on September 24, 2009. Retrieved September 1, 2017.
- ^ "Honolulu Rail: The Complete Final Environmental Impact Statement". June 16, 2010. Archived from the original on September 1, 2017. Retrieved September 1, 2017.
- ^ Honolulu Authority for Rapid Transit, "System Figures", honolulutransit.org, archived from the original on July 29, 2014, retrieved July 22, 2014
- ^ a b Kuriowa, Jared (August 18, 2016). "HART CEO Grabauskas resigns, Formby steps in as interim". KHON2. Honolulu. Retrieved January 11, 2019.[dead link ]
- ^ Tim Sakahara, "Concrete poured on Honolulu rail project Archived September 27, 2020, at the Wayback Machine," Hawaii News Now, May 16, 2012, retrieved on October 29, 2014.
- ^ a b "HART Recovery Plan" (PDF). Honolulu Authority for Rapid Transportation. April 28, 2017. p. 19. Archived (PDF) from the original on August 31, 2017. Retrieved August 31, 2017.
- ^ "HART cancels bids for first 9 rail stations". KITV. September 10, 2014. Archived from the original on November 29, 2014. Retrieved November 27, 2014.
- ^ "Year in Review 2015: Honolulu's rail transit project". Pacific Business Review. December 15, 2015. Archived from the original on September 5, 2017. Retrieved September 5, 2017.
- ^ "Honolulu Rail Price Estimate Jumps To $6.9B". Civil Beat News. May 14, 2016. Archived from the original on May 15, 2016. Retrieved May 16, 2016.
- ^ "City audit calls HART's finances, plans 'outdated and unreliable'". KHON2. April 15, 2016. Archived from the original on September 5, 2017. Retrieved September 4, 2017.
- ^ "Audit slams Honolulu rail agency over management, costs". Honolulu Star Advertiser. April 15, 2016. Archived from the original on September 5, 2017. Retrieved September 4, 2017.
- ^ "Add 5 years and $1B for rail, federal agency says". Honolulu Star-Advertiser. May 17, 2016. Archived from the original on June 11, 2016. Retrieved December 10, 2017.
- ^ Honoré, Marcel (August 18, 2016). "Grabauskas resigns as HART's chief executive". Star-Advertiser. Honolulu. Archived from the original on October 23, 2018. Retrieved January 11, 2019.
- ^ Daysog, Rick; Kawano, Lynn (August 18, 2016). "Outgoing rail CEO ruffled feathers, struggled with cost overruns". Hawaii News Now. Honolulu. Archived from the original on January 12, 2018. Retrieved January 11, 2019.
- ^ a b Shimogawa, Duane (December 28, 2016). "Former HART CEO Dan Grabauskas starts own consulting firm". Pacific Business News. Honolulu. Archived from the original on September 22, 2020. Retrieved January 11, 2019.
- ^ Honoré, Marcel (July 31, 2017). "HART board selects new executive director". Star-Advertiser. Honolulu. Archived from the original on July 31, 2017. Retrieved January 11, 2019.
- ^ Pennybacker, Mindy (January 9, 2020). "Honolulu's rail will be ready to run by Oct. 20, HART chief Andrew Robbins says". Honolulu Star-Advertiser. Archived from the original on October 5, 2020. Retrieved September 11, 2020.
- ^ "Editorial: COVID-19 brings more delays and money problems for Honolulu's rail". Honolulu Star-Advertiser. May 16, 2020. Archived from the original on October 4, 2020. Retrieved September 20, 2020.
- ^ Dayton, Kevin (June 26, 2020). "Scheduled 2025 opening date for 20-mile rail line being pushed into 2026". Honolulu Star-Advertiser. Archived from the original on September 17, 2020. Retrieved September 10, 2020.
- ^ "Rail's P3 Proposals Finally Arrive But Costs Remain Sealed". Honolulu Civil Beat. July 25, 2020. Archived from the original on September 16, 2020. Retrieved September 10, 2020.
- ^ "Honolulu Rail P3 Bidder Wants More Than $2 Billion For The Final Stretch". Honolulu Civil Beat. September 18, 2020. Archived from the original on September 28, 2020. Retrieved September 20, 2020.
- ^ "Rail swells to $10B to build and finance, gap now $1.2B as tax sinks". KHON2. October 16, 2020. Archived from the original on October 25, 2020. Retrieved November 3, 2020.
- ^ Pang, Gordon Y. K. (November 18, 2020). "Mayor Kirk Caldwell: Rail cost now $11B, won't be completed until 2033". Honolulu Star-Advertiser. Archived from the original on November 27, 2020. Retrieved November 28, 2020.
- ^ "How Rail Got to $12.45 Billion and 11 Years Late". Hawaii Business Magazine. November 9, 2021. Retrieved April 28, 2023.
- ^ Rodriguez, Max (March 31, 2022). "Honolulu rail project gets estimated time arrival". KHON2. Archived from the original on April 21, 2022. Retrieved April 20, 2022.
- ^ "Summer 2022 is the earliest the rail could begin partial operations, HART CEO says". Hawai'i Public Radio. December 10, 2021. Retrieved April 28, 2023.
- ^ Ufi, Elizabeth (April 13, 2022). "Rail repairs made from Kapolei to Aloha Stadium". KHON2. Archived from the original on April 21, 2022. Retrieved April 20, 2022.
- ^ Solina, Samie (June 9, 2022). "People could be riding the Honolulu rail by the end of 2022, HART's CEO says". Hawaii News Now. Retrieved April 28, 2023.
- ^ "HART begins trial running on Honolulu rail line". Mass Transit. Honolulu, Hawaii. August 31, 2022. Retrieved September 23, 2022.
- ^ "'Let's get ready to ride': city officials prepare to roll out Honolulu rail on June 30". Hawai'i Public Radio. May 10, 2023. Retrieved May 14, 2023.
- ^ Wanek-Libman, Mischa (May 22, 2023). "Honolulu's rail line will open June 30: The first nine stations will connect East Kapolei to Aloha Stadium with two planned extensions in 2025 and 2031". Mass Transit Magazine. Archived from the original on May 22, 2023. Retrieved May 22, 2023.
- ^ Kabir, Shanila (June 16, 2023). "Oahu's upcoming rail system is officially named 'Skyline'". KITV. Retrieved June 17, 2023.
- ^ Bauer, Ian (June 16, 2023). "City officials give Honolulu rail system an official name". Honolulu Star-Advertiser. Retrieved June 17, 2023.
- ^ Honolulu Department of Transportation Services (May 1, 2024). How the Manu o Kū influenced Skyline. Retrieved June 15, 2024 – via YouTube.
- ^ "Good monster film ruined by humans". Honolulu Star-Advertiser. May 16, 2014. Retrieved May 21, 2024.
- ^ Godzilla (2014) – Monorail Fight Scene (3/10). YouTube. March 2, 2020. Retrieved November 22, 2022.
External links
[edit]- Honolulu Department of Transportation Services operation website
- HART website
- Media related to Skyline (Honolulu) at Wikimedia Commons
- Skyline (Honolulu)
- Transportation in Honolulu
- 2023 establishments in Hawaii
- Rail transportation in Hawaii
- Passenger rail transportation in Hawaii
- Railway lines opened in 2023
- 750 V DC railway electrification
- Rapid transit in Hawaii
- Standard gauge railways in the United States
- Rail infrastructure under construction